PK0-004 FORMULAS CORRECTLY ANSWERED GRADED A+
- Grado
- Institución
PK0-004 FORMULAS CORRECTLY ANSWERED GRADED A+Estimate at Completion (EAC) An estimate of what it will cost to complete the project based on performance to date EAC = BAC/CPI Estimate to Complete (ETC) The expected cost to finish all the remaining project work. ETC=EAC-AC Variance ...