ion 1 (tb.ProjectPlSG2E.c05.07) Which of the following is true for float? A. It’s calculated by adding the durations of all tasks and dividing by the number of tasks. B. It’s time that you add to the project schedule to provide a buffer or contingency. D. It is calculated only on the lon...