Exam Latest 2025\2026 With Complete
Questions and Correct Answers Graded A+
Project management is ideally suited for a business environment requiring all of
the following EXCEPT
a. Repeatability.
b. Accountability.
c. Innovation.
d. Flexibility.
e. Speed. - CORRECT ANSWERa. repeatability
,Which of the choices listed below is NOT considered to be a characteristic of a
project?
a. For internal use only
b. An established objective
c. Specific time, cost and performance requirements
d. A clear beginning and end
e. Something never been done by a particular company before - CORRECT
ANSWERa. for internal use only
Project management is not limited to the __________ sector.
a. private
b. international
c. universal
d. business and government
e. global - CORRECT ANSWERa. private
,Which of the following represents the correct order of stages within the project
life cycle?
a. Defining, Planning, Executing, Closing
b. Planning, Defining, Closing, Executing
c. Executing, Defining, Planning, Closing
d. Planning, Defining, Executing, Closing
e. Closing, Planning, Defining, Executing - CORRECT ANSWERa. Defining,
Planning, Executing, Closing
A project life cycle
a. must be dogmatically followed.
b. will always have a phase called 'visioning'.
c. reduces the amount of planning necessary.
d. can vary based on the industry.
e. will only ever consist of four phases. - CORRECT ANSWERd. can vary based
on the industry.
, Which of these is NOT part of the "sociocultural dimension" of project
management?
a. Managing customer expectations
b. Leadership
c. Resource allocation
d. Dealing with politics
e. Negotiation - CORRECT ANSWERc. Resource allocation
Any project life cycle is made up of stages. The project's schedule and budget will
be determined in the ___________ stage of the project life cycle.
a. planning
b. defining
c. executing
d. closing
e. conceptual - CORRECT ANSWERa. planning
Training the customer, releasing staff and resources occurs in the ________ stage
of project life cycle.