Question 1. What is the primary purpose of a building permit in
North Carolina?
A) To collect revenue for the municipality
B) To ensure code compliance prior to construction
C) To guarantee contractor quality
D) To establish property values
Answer: B
Explanation: Permits are required to ensure that construction
complies with the North Carolina State Building Code and other
applicable laws before work begins.
Question 2. Which permit type is required for the removal of an
entire building structure?
A) Mechanical permit
B) Demolition permit
C) Electrical permit
D) Foundation permit
Answer: B
, NC Building Level III Inspector Exam
Explanation: A demolition permit is specifically required for the
removal or demolition of whole or partial structures.
Question 3. At which stage is the first required inspection
typically conducted for a new building?
A) Framing
B) Footing
C) Final
D) Insulation
Answer: B
Explanation: The footing inspection is usually the first
inspection, verifying foundation excavation and reinforcement
before concrete is poured.
Question 4. Who is responsible for issuing a stop-work order on
a project site?
A) The property owner
B) The general contractor
C) The code official
, NC Building Level III Inspector Exam
D) The architect
Answer: C
Explanation: The code official has authority to issue stop-work
orders when work is being done contrary to approved plans or
code.
Question 5. Under North Carolina law, which document
establishes the responsibilities and authority of the code
official?
A) Local zoning ordinance
B) General Statutes
C) International Building Code
D) Labor law
Answer: B
Explanation: North Carolina General Statutes outline the duties
and powers of code officials.
Question 6. Which of the following is a duty of the code
official?
, NC Building Level III Inspector Exam
A) Designing the building
B) Supervising construction crews
C) Enforcing building codes
D) Providing legal representation
Answer: C
Explanation: The code official enforces building codes and
regulations, not design or construction.
Question 7. What action is required when a violation of the
Building Code is identified during inspection?
A) Ignore the violation
B) Issue a notice of violation
C) Continue with the inspection only
D) Stop the project immediately
Answer: B
Explanation: A notice of violation must be issued, detailing the
problem and corrective action required.