Splices in rall tracks shall have - ANSWER Smooth Joints Hydraulic systems should have their proper fluid level checked - ANSWER Daily If power fails during operations, the following shouldn't apply - ANSWER Do your best to finish moving load where it was designated to go If load is undetermined who is to find out if load weight does not exceed crane rating at radius at which the load is to be lifted - ANSWER Person responsible for lift Where should climbing instructions be kept - ANSWER ON Site Chain slings are required to be - ANSWER ID tagged Welding on loads suspended by the crane can only be done if the load has - ANSWER Insulated slings How much does an average cubic yard of concrete weight - ANSWER 4,000 lbs Main power switch for tower crane is - ANSWER At base of crane Items not listed in the frequent inspection checklist are - ANSWER Hydraulic pumps and valves for excessive wear or damage When is it necessary to determine that there is no practical alternative way to perform the needed work or to gain access to the area - ANSWER Personnel Lift Each series of voice signals shall contain three elements stated in the following order - ANSWER Function and Direction - Distance and speed - Function stop

Show more Read less
Institution
NCCCO
Course
NCCCO










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NCCCO
Course
NCCCO

Document information

Uploaded on
September 24, 2024
Number of pages
19
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

NCCCO tower crane
flashcards COMPLETE
QUESTIONS AND
SOLUTIONS(LATEST
UPDATE 2024)
Splices in rall tracks shall have - ANSWER Smooth Joints


Hydraulic systems should have their proper fluid level checked - ANSWER Daily


If power fails during operations, the following shouldn't apply - ANSWER Do your
best to finish moving load where it was designated to go


If load is undetermined who is to find out if load weight does not exceed crane
rating at radius at which the load is to be lifted - ANSWER Person responsible for
lift


Where should climbing instructions be kept - ANSWER ON Site

, Chain slings are required to be - ANSWER ID tagged


Welding on loads suspended by the crane can only be done if the load has -
ANSWER Insulated slings


How much does an average cubic yard of concrete weight - ANSWER 4,000 lbs


Main power switch for tower crane is - ANSWER At base of crane


Items not listed in the frequent inspection checklist are - ANSWER Hydraulic
pumps and valves for excessive wear or damage


When is it necessary to determine that there is no practical alternative way to
perform the needed work or to gain access to the area - ANSWER Personnel Lift


Each series of voice signals shall contain three elements stated in the following
order - ANSWER Function and Direction - Distance and speed - Function stop


When lifting personnel communication shall be maintained between three of the
next four - ANSWER Person(s) being lifted - Operator - Signal person


The condition when the tower load block or hook assembly comes in contact with
the upper - ANSWER Two-blocking

, Load bearing members of the climbing and support system shall be inspected
before each - ANSWER Climbing operation


Where shall a wind velocity indicating device be mounted - ANSWER At or near
the top of crane


According to ASME B30.3, the prohibited zone for power lines that are 60kV is -
ANSWER 15ft. ASME 3-3.3.4.3(1) Table 1


According to ASMA 30.3, load hoist rotation resistant wire rope has a design factor
of - ANSWER 5 to 1 ASME 3-1.5.5(b)


According to ASME B30.3, when lifting a suspended personnel platform the design
factor for the rigging hardware is - ANSWER 5 to 1 ASME 3-3.2.2(b)(3)


According to ASME B30.3, Load hoist ropes that are not rotation must have a
design factor of - ANSWER 5 to 1 ASME 3-1.5.5(b)
All climbing operations shall be performed under the supervision of - ANSWER
Qualified person


When cranes are erected, load limiting devices shall be tested for proper setting
and operation - ANSWER Before crane is placed in service


Hooks shall be equipped with latches unless the application makes the use of the
latch - ANSWER Impractical
CA$22.18
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Exampool NURSING
Follow You need to be logged in order to follow users or courses
Sold
219
Member since
2 year
Number of followers
147
Documents
3591
Last sold
1 month ago
Power-horse Library

HELLO Dear ones On this Account you will find all Study related Materials ,EXAMS, STUDY GUIDES, CASES,NOTEBOOKS and many more. well come as we study for Excellency.

3.9

32 reviews

5
16
4
2
3
10
2
2
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions