1. What is the primary purpose of building commissioning?
A. Increase construction speed
B. Ensure systems are installed according to design intent
C. Reduce material costs
D. Replace building inspection
Rationale: Commissioning verifies that building systems meet
the owner's requirements and design specifications.
Correct answer: B
2. Who is typically responsible for leading the commissioning
process?
A. General contractor
B. Commissioning authority
C. Architect
D. Facility manager
Rationale: The commissioning authority oversees planning,
testing, and verification.
Correct answer: B
,3. What document defines the owner’s project requirements
(OPR)?
A. Construction schedule
B. Owner’s Project Requirements document
C. Punch list
D. Submittal log
Rationale: The OPR outlines functional and performance
expectations of the building.
Correct answer: B
4. What does HVAC commissioning primarily verify?
A. Aesthetic design
B. System performance and efficiency
C. Construction speed
D. Material color matching
Rationale: HVAC commissioning ensures systems operate
according to design and efficiency standards.
Correct answer: B
5. What is a functional performance test (FPT)?
A. A financial audit
B. A test of system operation under real conditions
C. A material strength test
D. A design review meeting
,Rationale: FPT evaluates system behavior under expected
operating conditions.
Correct answer: B
6. Which phase includes commissioning planning?
A. Occupancy phase
B. Construction phase only
C. Pre-design phase
D. Post-demolition phase
Rationale: Commissioning planning begins early, often in pre-
design or design phase.
Correct answer: C
7. What is the role of a commissioning checklist?
A. Track labor hours
B. Verify system installation steps
C. Approve budgets
D. Replace drawings
Rationale: Checklists ensure systems are installed correctly and
completely.
Correct answer: B
8. What is a common HVAC system component verified during
commissioning?
, A. Paint finish
B. Air handling unit
C. Roofing membrane
D. Flooring adhesive
Rationale: Air handling units are critical HVAC components
requiring commissioning.
Correct answer: B
9. What does TAB stand for in commissioning?
A. Thermal Air Balance
B. Testing, Adjusting, and Balancing
C. Technical Assessment Board
D. Total Air Build
Rationale: TAB ensures HVAC systems deliver correct airflow
and performance.
Correct answer: B
10. What is the purpose of a commissioning plan?
A. Define construction costs
B. Outline commissioning process and responsibilities
C. Replace architectural drawings
D. Approve permits