BUNDLED EXAM 2026 COMPREHENSIVE
REVIEW RESOURCE
⫸ What is the use of a procedure that is inconsistent with the FAR?
Answer: Deviation
⫸ Simplified Acquisition Procedures (SAP) should? Answer: Promote
competition to the maximum extent practicable
⫸ What is the tool (form) used by DoD to apply a structured profit/fee?
Answer: DD Form 1547, Weighted Guidelines Method
⫸ What type(s) of contracts can be awarded when acquiring commercial
items of supply? Answer: Only firm-fixed-price contracts or fixed-price
contracts with economic price adjustment
⫸ When using invitations for bids (IFBs), what type(s) of contracts can
be awarded? Answer: Only firm-fixed-price contracts or fixed-price
contracts with economic price adjustment
⫸ Which of the following is correct regarding the DFARS Procedures
Guidance and Information (PGI)? Answer: The DFARS PGI is a
companion resource to the DFARS
, ⫸ Which of the following statements is accurate regarding the
Government's policy on contract modifications? Answer: Only
contracting officers acting within the scope of their authority are
authorized to execute contract modifications on behalf of the
Government
⫸ Which of the following is accurate about unilateral modifications?
Answer: Are only signed by a Government contracting officer, not the
contractor
⫸ Except when authorized otherwise, a Government contract? Answer:
Must be in writing
⫸ Which is NOT a type of contracting officer? Answer: Executive
contracting officer
⫸ With respect to the requirements of law, executive orders,
regulations, and all other applicable procedures, prior to signing a
contract, a contracting officer must? Answer: Ensure that each has been
met
⫸ Joan stated that she was working on selecting solicitation provisions.
With this in mind, you know the contract? Answer: Has not been
awarded
⫸ A program manager asked John whether a contract clause is only
used in the contract or if it applies to the solicitation as well. John