And Answers Verified 100% Correct
Where in the FAR can you find guidance on how to establish, maintain, and
dispose of Government contract files? - ANSWER -FAR Part 4 (Administrative &
Information Matters)
Which FAR Part is the best source of information regarding competition
requirements? - ANSWER -FAR Part 6 (Competition Requirements)
Where is in the FAR is contracting by negotiation covered? - ANSWER -FAR
Part 15
Contractors are required to certify that a claim is made in good faith when
submitting any claim exceeding: - ANSWER -$100,000
One of the proper protest venues is the: - ANSWER -U.S. Court of Federal Claims
What FAR Part covers protest/ - ANSWER -FAR Part 33
Which FAR part is titled "Subcontracting Policies and Procedures"? - ANSWER -
FAR Part 44
You've received a claim on your contract. The contractor is required to certify its
claim above what amount? - ANSWER -$100,000
What FAR Part covers terminations? - ANSWER -FAR Part 49
What FAR Part is Special Contracting Methods? - ANSWER -FAR Part 17
What FAR Part has bonds and insurance? - ANSWER -FAR Part 28
Emergency Acquisitions is which FAR Part? - ANSWER -FAR Part 18
,What is FAR Part 5? - ANSWER -Publicizing Contract Actions
What is FAR Part 2? - ANSWER -Definitions of Words and Terms
What is FAR Part 3? - ANSWER -Improper Business Practices and Personal
Conflicts of Interest
What is FAR Part 11? - ANSWER -Describing Agency Needs
What is FAR Part 10? - ANSWER -Market Research
What is FAR Part 7? - ANSWER -Acquisition Planning
What is FAR Part 53? - ANSWER -Forms
What FAR Part has Provisions & Contract Clauses? - ANSWER -FAR Part 52
Termination of Contracts is which FAR Part? - ANSWER -FAR Part 49
What FAR Part is Quality Assurance? - ANSWER -FAR Part 46
What is FAR Part 45? - ANSWER -Government Property
What is FAR Part 44? - ANSWER -Subcontracting Policies and Procedures
What is FAR Part 43? - ANSWER -Contract Modifications
What is FAR Part 42? - ANSWER -Contract Administration and Audit Services
What is FAR Part is 33? - ANSWER -Protests, Disputes & Appeal
What is FAR Part 31? - ANSWER -Contract Cost Principles and Procedures
What is FAR Part 9? - ANSWER -Contractor Qualifications
, What is FAR Part 15? - ANSWER -Contracting by Negotiation
What is FAR Part 4? - ANSWER -Administrative and Information Matters
What is FAR Part 13? - ANSWER -Simplified Acquisition Procedures
What is FAR Part 19? - ANSWER -Small Business Programs
What is FAR Part 12? - ANSWER -Acquisition of Commercial Items
What is FAR Part 16? - ANSWER -Types of Contracts
What is FAR Part 8? - ANSWER -Required Sources of Supplies and Services
What is FAR Part 14? - ANSWER -Sealed Bidding
FAR 13.004 states that ________________ - ANSWER -a quotation is not an
offer, and consequently, cannot be accepted by the government to form a binding
contract.
FAR 13.106-2(a)(2) tells us that the contracting officer shall evaluate quotations
or offers on the __________ - ANSWER -basis established in the solicitation
What are the two broad categories of contract types? - ANSWER -Cost
reimbursement
Fixed Price
True or False: A cost reimbursement type contract places upon the contractor
maximum risk and responsibility for all costs and resulting profit or loss. -
ANSWER -False
True or False: Cost-reimbursement types of contracts require the contractor to put
forth a best effort to perform, and provide for payment of the contractor's
allowable, allocable and reasonable incurred costs. - ANSWER -True