Pull communication is used to send information to specific recipients who need to
receive the information
Give this one a try later!
False
Tools and techniques for Develop Project Team include:
, Give this one a try later!
Interpersonal skills & Negotiation
As part of the communication process, the sender is responsible for making the
information clear and complete so that the receiver can receive it correctly, and the___
is(also) responsible for ensuring that the information is received in its entirety,
understood correctly, and acknowledged or responded to appropriately
Give this one a try later!
Receiver
Project managers should recognize the following characteristics of conflict:
Give this one a try later!
None of the above
____ is an optimization technique in which start and finish dates are adjusted based on
resource constraints. It can be used when shared or critical required resources are
only available at certain times, in limited quantities, or to keep resource usage at a
constant level. It can often cause the original critical path to change, usually to
increase.
Give this one a try later!
receive the information
Give this one a try later!
False
Tools and techniques for Develop Project Team include:
, Give this one a try later!
Interpersonal skills & Negotiation
As part of the communication process, the sender is responsible for making the
information clear and complete so that the receiver can receive it correctly, and the___
is(also) responsible for ensuring that the information is received in its entirety,
understood correctly, and acknowledged or responded to appropriately
Give this one a try later!
Receiver
Project managers should recognize the following characteristics of conflict:
Give this one a try later!
None of the above
____ is an optimization technique in which start and finish dates are adjusted based on
resource constraints. It can be used when shared or critical required resources are
only available at certain times, in limited quantities, or to keep resource usage at a
constant level. It can often cause the original critical path to change, usually to
increase.
Give this one a try later!