◉ What are the characteristics of a Development Team? Select three
most appropriate choices.
Scrum recognizes no sub-teams in the Development Team
Having the Scrum Master as a part-time Developer in the
Development Team
Having at least one test engineer in the Development Team
Accountability belongs to the Development Team as a whole
Scrum recognizes no titles for Development Team members
Answer: Scrum recognizes no sub-teams in the Development team
Accountability belongs to the Development team as a whole
Scrum recognizes no titles for Development team member
,◉ Only the Product Owner and the Development Team participate in
the Sprint Planning. There is nothing to do for the Scrum Master.
True/False Answer: False - this plan is created by the entire scrum
team
◉ What happens during the Sprint? Select three answers.
Sprint scope is defined at the Sprint Planning and cannot be changed
Scope may be clarified and re-negotiated between the Product
Owner and Development Team as more is learned
No changes are made that would endanger the Sprint Goal
The Sprint Goal is changed frequently to reflect the status of the
remaining work
Quality goals do not decrease Answer: Scope may be clarified and
re-negotiated between the Product Owner and Development Team
as more is learned
,No changes are made that would endanger the Sprint Goal
Quality goals do no decrease
◉ Who participates in the Sprint Planning? Select three.
The Development Team
The Product Owner
The Team Manager
The Key Stakeholders
The Scrum Master Answer: The Development team
The product Owner
The Scrum Master
◉ Imagine you are a Scrum Master in a small Organization that tries
to adopt Scrum. There are 10 developers and the Product Owner.
How can they be divided into teams? Choose all applicable options
1 team of 10 people (because there is no reason to divide)
, 2 teams of 6 and 4 people (after a short meeting the developers
decided this is the best option)
3 teams of 4, 3 and 3 people (each team is cross-functional)
2 teams of 6 and 4 people (because it is good to have a separate QA
team) Answer: 2 teams of 6 and 4 people (after a short meeting the
developers decided this is the best option)
3 teams of 4, 3 and 3 people (each team is cross-functional)
◉ Sort Scrum events in the right order.
Sprint Planning
Daily Scrum
Sprint Review
Sprint Retrospective Answer: Sprint Planning
Daily Scrum
Sprint Review
Sprint Retrospective
◉ Check all the formal opportunities to inspect and adapt.