LAB TEST
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration? A. Two B. Four C. Five D. Twelve Hide Answer Question No : 679 - Topic 5 When a permitting agency takes longer than planned to issue a permit, this can be described as a risk: A. event. B. response, C. perception. D. impact. Hide Answer Question No : 680 - Topic 5 Answer: A T