• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 4 fuera de 238 páginas
Examen

CAPM Practice Exam Questions With Complete Solutions

Document preview thumbnail
Vista previa 4 fuera de 238 páginas

CAPM Practice Exam Questions With Complete Solutions

Vista previa del contenido

CAPM Practice Exam Questions With Complete Solutions

A key resource is assigned to work on a project using a hybrid
approach. The project has kicked off, and work has begun. This
resource lives in another country and cannot move to the United
States to work in the office for three months. What should the
project manager do in this situation?

a. Hire an external vendor to complete this portion of the work.
b. Delay the project until the resource is available to be in the
office.
c. Train another member of the team so that they can complete
this work.
d. Request that the team member work remotely until they can
move into the country. Correct Answers d. Request that the
team member work remotely until they can move into the
country.

Explanation:
Because the resource is living in another country, it would be
best to have this resource work remotely until they can arrive in
the country. This would be a better alternative than rescheduling
the work and possibly delaying the project.

Domain:
I. Project Management Fundamentals and Core Concepts
Objective:
04 - Development Approach and Life Cycle Performance
Domain

,A key stakeholder approaches you and says that there is a
missing requirement that they want incorporated without going
through a formal change control process. What do you do next?

a. Escalate to the project sponsor.
b. Accommodate the request because it is coming from a key
stakeholder.
c. Assess the impact of the requirement and submit it through
the formal change control process.
d. Negotiate with the key stakeholder to remove less valuable
requirements in exchange for this new request. Correct Answers
c. Assess the impact of the requirement and submit it through
the formal change control process.

Explanation:
Changes to a project should always be assessed and evaluated
and brought through change control.

Domain:
IV. Business Analysis Frameworks
Objective:
10 - Business Analysis Frameworks

A key stakeholder has asked you for an update on the adaptive
project you are working on. They are specifically asking how
much work remains in the current iteration. What do you direct
the stakeholder to?

a. Iteration burnup chart
b. Iteration burndown chart
c. Project schedule

,d. Work breakdown structure Correct Answers b. Iteration
burndown chart

Explanation:
An iteration burndown chart shows the work remaining in the
iteration. An iteration burnup chart shows the work completed
so far in the iteration. The other two options are used in
predictive projects.

Domain:
III. Agile/Adaptive Frameworks and Methodologies
Objective:
07 - Planning, Project Work, and Delivery: Adaptive
Approaches

A key stakeholder on an adaptive project is confused about the
product roadmap and a release plan and asks you to clarify. How
do you explain this?

a. A product roadmap contains the high-level requirements and
epics broken up into releases; a release plan showcases the
number of iterations needed to deliver certain features and user
stories decomposed from epics.
b. A release plan contains the high-level requirements and epics
broken up into products; a product roadmap showcases the
number of iterations needed to deliver certain features and user
stories decomposed from epics.
c. A product roadmap is a highly detailed plan, and a release
plan is very high level.
d. A product roadmap and release plan are used only when scope
and schedule baselines are still not defined. Correct Answers a.

, A product roadmap contains the high-level requirements and
epics broken up into releases; a release plan showcases the
number of iterations needed to deliver certain features and user
stories decomposed from epics.

Explanation:
A product roadmap acts as a high-level summary of a product's
alignment to strategic initiatives and objectives. A product
roadmap generally contains themes, epics, and goals broken up
into releases. A release plan decomposes a product roadmap's
high-level strategy into an actionable plan that outlines specific
release dates for work on features, user stories, bug fixes,
enhancements, maintenance, and so on. Essentially, a release
plan sets the number of iterations within a release and which
features are to be developed during that time frame.

Domain:
IV. Business Analysis Frameworks
Objective:
11 - Business Analysis Domains

A key stakeholder reviewed the product roadmap document,
hoping to see which iterations will deliver specific features
throughout the adaptive project. Instead, all the stakeholder saw
was high-level and strategic information about the product's
deliverables, with very broad date ranges. What document
should you tell the stakeholder to refer to instead?

a. The project management plan
b. The product backlog
c. The release plan

Información del documento

Subido en
12 de noviembre de 2025
Número de páginas
238
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$31.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Classroom
4.0
(1211)
Vendido
5006
Seguidores
3246
Artículos
56710
Última venta
6 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes