100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

U1 UST Installation/Retrofitting Exam Questions And Answers Verified 100% Correct

Puntuación
-
Vendido
-
Páginas
17
Grado
A+
Subido en
16-10-2025
Escrito en
2025/2026

U1 UST Installation/Retrofitting Exam Questions And Answers Verified 100% Correct Carefully inspect _______________ and __________________ surfaces of a tank shipped with a liquid-filled interstice for signs of leakage - ANSWER Interior, exterior A double-walled tank shipped with a _____________ on the interstice need not be subjected to an air/soap test. - ANSWER A. Ballard B. Gauge C. Skid D. Vacuum ANSWER D . To avoid undermining foundations of existing structures excavation must be done - ANSWER A. Carefully B. Tentatively C. Quickly D. Efficiently ANSWER A What is the determinant of the total depth of the tank excavation. - ANSWER A. Tank diameter, bedding-thickness, hold-down pad(If required), depth of cover, and slope and length of piping. B. Slope and length of piping, depth of cover, hold down pad(If required), thickness, amount of dirt C. Thickness, hold-down pad(If required), depth of cover, bedding, previous leaks or spills D. Slope and length of piping, thickness, amount of dirt, depth of cover, bedding, thickness. ANSWER A Much of a buried tanks support is derived from __________ - ANSWER A. Compacted backfill B. Chain-falls C. Reinforced steal walls D. Concrete ANSWER A _______ ____________ are geotextiles designed to prevent movement of back-fill materials, while permitting water to pass through - ANSWER Filter fabrics To provide a firm foundation for the tank, set the tank on a bed of ___________ material one foot thick that extends one foot beyond the ends and sides of the tank. - ANSWER backfill . ___ feet of backfill must be placed between adjacent tanks and between tanks and excavation walls. - ANSWER A. 1 B. 2 C. 3 D. 4 ANSWER B In areas subject to vehicle traffic, cover may consist of at least _________ inches of compacted backfill and ________ inches of asphaltic concrete, or___________ inches of reinforced concrete - ANSWER 30, 6, 18 Maximum burial depth, measured from the top of the tank, are established by tank __________ and ________________ - ANSWER A. Manufacturers and the installers B. Independent testing laboratories C. Installers and independent testing labs D. Installers and the tank owner E. Manufacturers F. Both B and E ANSWER F . For fiberglass tanks ______ feet is the standard max depth for the tank - ANSWER 7 ________ feet is the typical burial depth for steel tanks - ANSWER 5 Excavated materials that cannot be immediately removed from the site should be safely stockpiled at least _______ feet away from the edge of the tank excavation - ANSWER 2 Common deficiencies that adversely affect the structural integrity and coating of tanks include - ANSWER A. use of incorrect backfill material B. Inadequate or improper placement or compaction of backfill materials C. rocks of debris left in the excavation D. Voids under the lower quadrant of the tank E. Failure to prevent migration of backfill materials F. All of the above ANSWER F 55. If a product is used for ballast do not fill tank about _______ percent ? - ANSWER 95 56. Water in a storage tank can promote internal _____________ and degrade fuel quality. - ANSWER Corrosion 57 . Back fill material should be - - i B. A Morph s C. Egregious D. Free flowing ANSWER D 58 - ANSWER A. Stagnate . Cover the bottom of the excavation with suitably graded and properly placed back fill material to a depth of at least _________ Foot/feet deep B. 1 foo t C. 1.5 Fee t D. 2 Fee ANSWER B - ANSWER A. 0.5 Foot t 59. What are the standard back fill materials for a fiberglass tank. - ANSWER A. pea gravel and crushed rock B. pea gravel and dirt C. pea gravel and water D. sawdust and pea gravel ANSWER A 60. When dealing with a fiberglass tank the bottom of the excavation or hold-down pad must be covered with a minimum of ______ foot/ feet of suitably graded and compacted back fill material. - ANSWER A. 10 B. 3 C. 1 D. 2 ANSWER C 61. Place sand and back fill into the excavation in twelve to eighteen inch lifts and compact after each lift. Repeat this process up to at least _________ % of the tank. - ANSWER A. 60 B. 65

Mostrar más Leer menos
Institución
U1 UST Installation/Retrofitting
Grado
U1 UST Installation/Retrofitting










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
U1 UST Installation/Retrofitting
Grado
U1 UST Installation/Retrofitting

Información del documento

Subido en
16 de octubre de 2025
Número de páginas
17
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

U1 UST Installation/Retrofitting Exam Questions And
Answers Verified 100% Correct
Carefully inspect _______________ and __________________ surfaces of a tank
shipped with a liquid-filled interstice for signs of leakage - ANSWER Interior, exterior

A double-walled tank shipped with a _____________ on the interstice need not be
subjected to an air/soap test. - ANSWER A. Ballard
B. Gauge
C. Skid
D. Vacuum
ANSWER D

. To avoid undermining foundations of existing structures excavation must be done -
ANSWER A. Carefully
B. Tentatively
C. Quickly
D. Efficiently
ANSWER A

What is the determinant of the total depth of the tank excavation. - ANSWER A. Tank
diameter, bedding-thickness, hold-down pad(If required), depth of cover, and slope and
length of piping.

B. Slope and length of piping, depth of cover, hold down pad(If required), thickness,
amount of dirt

C. Thickness, hold-down pad(If required), depth of cover, bedding, previous leaks or
spills

D. Slope and length of piping, thickness, amount of dirt, depth of cover, bedding,
thickness.

ANSWER A

Much of a buried tanks support is derived from __________ - ANSWER A.
Compacted backfill
B. Chain-falls
C. Reinforced steal walls
D. Concrete
ANSWER A

,_______ ____________ are geotextiles designed to prevent movement of back-fill
materials, while permitting water to pass through - ANSWER Filter fabrics

To provide a firm foundation for the tank, set the tank on a bed of ___________ material
one foot thick that extends one foot beyond the ends and sides of the tank. - ANSWER
backfill

. ___ feet of backfill must be placed between adjacent tanks and between tanks and
excavation walls. - ANSWER A. 1
B. 2
C. 3
D. 4
ANSWER
B

In areas subject to vehicle traffic, cover may consist of at least _________ inches of
compacted backfill and ________ inches of asphaltic concrete, or___________
inches of reinforced concrete - ANSWER 30, 6, 18

Maximum burial depth, measured from the top of the tank, are established by tank
__________ and ________________ - ANSWER A. Manufacturers and the installers
B. Independent testing laboratories
C. Installers and independent testing labs
D. Installers and the tank owner
E. Manufacturers
F. Both B and E
ANSWER F

. For fiberglass tanks ______ feet is the standard max depth for the tank - ANSWER 7

________ feet is the typical burial depth for steel tanks - ANSWER 5

Excavated materials that cannot be immediately removed from the site should be safely
stockpiled at least _______ feet away from the edge of the tank excavation -
ANSWER 2

Common deficiencies that adversely affect the structural integrity and coating of
tanks include - ANSWER A. use of incorrect backfill material
B. Inadequate or improper placement or compaction of backfill materials
C. rocks of debris left in the excavation
D. Voids under the lower quadrant of the tank

, E. Failure to prevent migration of backfill materials
F. All of the above
ANSWER
F

55. If a product is used for ballast do not fill tank about _______ percent ? - ANSWER
95

56. Water in a storage tank can promote internal _____________ and degrade fuel
quality. - ANSWER Corrosion

57. Back fill material should be - ANSWER A. Stagnate
B. A-Morph-is
C. Egregious
D. Free flowing
ANSWER D

58. Cover the bottom of the excavation with suitably graded and properly placed back fill
material to a depth of at least _________ Foot/feet deep - ANSWER A. 0.5 Foot
B. 1 foot
C. 1.5 Feet
D. 2 Feet
ANSWER B

59. What are the standard back fill materials for a fiberglass tank. - ANSWER A. pea
gravel and crushed rock
B. pea gravel and dirt
C. pea gravel and water
D. sawdust and pea gravel
ANSWER
A

60. When dealing with a fiberglass tank the bottom of the excavation or hold-down pad
must be covered with a minimum of ______ foot/ feet of suitably graded and compacted
back fill material. - ANSWER A. 10
B. 3
C. 1 D. 2
ANSWER C

61. Place sand and back fill into the excavation in twelve to eighteen inch lifts and
compact after each lift. Repeat this process up to at least _________ % of the tank. -
ANSWER A. 60
B. 65
$13.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor
Seller avatar
TopGradeGuru
1.5
(2)

Conoce al vendedor

Seller avatar
TopGradeGuru Teachme2-tutor
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
10
Miembro desde
1 año
Número de seguidores
0
Documentos
2429
Última venta
1 mes hace
GRADEHUB

We provide access to a wide range of professionally curated exams for students and educators. It offers high-quality, up-to-date assessment materials tailored to various subjects and academic levels. With instant downloads and affordable pricing, it's the go-to resource for exam preparation and academic success.

1.5

2 reseñas

5
0
4
0
3
0
2
1
1
1

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes