According to the Florida Building Code, the distance in feet measured from the
building face to the closest interior lot line, to an alley or public way, to the
centerline of a street, or to an imaginary line between two buildings on the same
property is defined as:
A. Property line
B. Building line
C. Fire separation distance
D. Street line - ANSWER-C. Fire separation distance
According to the Florida Building Code, a car wash should be classified under
which Occupancy Group?
A. Group A
B. Group B
C. Group E
D. Group F - ANSWER-B. Group B
Construction or work for which a permit is required shall be subject to inspection
by the:
A. Building official
B. Owner
C. Architect
D. Engineer - ANSWER-A. Building Official
pg. 1
,The ________ shall determine the timing and sequencing of when inspections
occur and what elements are inspected at each inspection:
A. Owner
B. Architect
C. Contractor
D. Building Official - ANSWER-D. Building Official
The building foundation inspection is performed:
A. After trenches are excavated and forms erected and shall at a minimum include
the stem-wall and monolithic slab-on-grade.
B. After trenches are excavated and forms erected and shall at a minimum include
the stem-wall, monolithic slab-on-grade and piling/pile caps.
C. After trenches are excavated and forms erected and shall at a minimum include
the stem-wall, monolithic slab-on-grade, piling/pile caps, footers/grade beams
D. After trenches are excavated and forms erected and shall at a minimum include
the stem-wall, monolithic slab-on-grade, piling/pile caps, footers/grade beams, and
soil termite treatment - ANSWER-C. After trenches are excavated and forms
erected and shall at a minimum include the stem-wall monolithic slab-on-grade,
piling/pile caps, footers/grade beams
According to Florida Building Code, what are the minimum inspections required
for a building (exclusive of electrical, plumbing, mechanical and gas) made by the
Building Official)?
A. Excavation, framing, final and swimming pool
B. Foundation, framing, sheathing, roofing and final
C. Foundation, forms, insulation and final
D. Structural, foundation, framing and dry-in inspection - ANSWER-B.
Foundation, framing, sheathing, roofing and final
pg. 2
,For a typical building under construction, which building inspection usually
precedes the final inspection on the building?
A. Sheathing inspection
B. Framing inspection
C. Roofing inspection
D. Drywall inspection - ANSWER-C. Roofing inspection
According to the Florida Building Code, what is the proper order of the electrical
inspection?
A. Underground inspection, rough-in inspection, final inspection
B. Rough-in inspection, underground inspection, final inspection
C. Underground inspection, final inspection, rough-in inspection
D. Rough-in inspection, final inspection, underground inspection - ANSWER-A.
Underground inspection, rough-in inspection, final inspection
According to Florida Building Code, to prevent the entry of birds, squirrels,
rodents, etc., openings into attic spaces of habitable buildings shall be covered with
screening, hardware cloth or equivalent with openings not exceeding:
A. 1/16"
B. 1/8"
C. 1/4"
D. 1/2" - ANSWER-C. 1/4"
Page 413
According to the Florida Building Code, the minimum corridor width used as a
means of egress for Group 1 - 2, Unrestrained occupancies, requiring the
movement of beds, shall be:
A. 44"
pg. 3
, B. 56"
C. 72"
D. 96" - ANSWER-D. 96"
Page 395
Which of the following is NOT true?
A. A Certificate of Completion allows the tenant to begin occupying spaces in a
shell building
B. A temporary Certificate of Occupancy allows tenants to occupy safe portions of
an incomplete building
C. New buildings may not be occupied until the Building Official issues a
Certificate of Occupancy
D. A Certificate of Completion allows utilities to be hooked up - ANSWER-A. A
Certificate of Completion allows the tenant to begin occupying spaces in a shell
building
What building material is installed to resist the free passage of flame to other areas
of the building through concealed spaces?
A. Fire wall
B. Fire partition
C. Fire damper
D. Fire blocking - ANSWER-D. Fire blocking
A masonry unit in which the net concrete cross-sectional area parallel to the
bearing surface is 75% or more is classified as a:
A. Semi-solid masonry unit
B. Solid masonry unit
C. Hollow core masonry unit
pg. 4