Critical Thinking step 1 - Answer -Problem Identification

-Visualization
-Fact Finding

Critical Thinking step 2 - Answer -Creative Thinking

-Green light thinking
-Brainstorming

Critical Thinking step 3 - Answer -Logical Analysis

-Red light thinking
-Reasoning

Critical Thinking step 4 - Answer -Decision Making

-Gaining consensus
-Decision Matrixes

Critical Thinking step 5 - Answer -Coordination

-Plan Implementation
-Control Stress

Planning - Answer -asks Who? What? Where? How?

Scheduling - Answer -Determines the When?

Stakeholders in Planning - Answer --Owner
-Design Team
-Builders
-Agencies
-Providers

Stakeholders in Scheduling - Answer -"Practitioners"

- Contractor
- Owners Rep

Notice to Proceed - Answer -"The construction phase shall be deemed to commence"
which is another way to say start or date.

, Substantial Completion - Answer -That point where what was constructed is fit for
occupancy and ready to be used for its intended purpose.

Issued by the Architect & Owner.

Liquidated Damages - Answer -damages that parties to a contract agree in advance
should be paid if the contract is breached

Activity - Answer -the performance of a task required to complete the project, such as
design of the steel frame, procure steel fabrication, delivery of the fabricated steel, and
erecting of the steel frame.

Duration - Answer -the estimated time required to perform an activity, the time should
include all resources assigned to the activity.

Relationships - Answer -Model the logical flow the work, showing each activity and one
or more activities that follow each activity.

Lag - Answer -is the amount of wait time between two tasks. Or in other words, it is the
amount of time by which a successor activity will be delayed.

Float = Slack - Answer -the amount of time an activity may be delayed without delaying
the completion date of the project

Milestones - Answer --Important items to watch
-Zero Duration (0 days)
-May trigger the beginning or end of a phase
-Examples: Contract signed, Construction start, Dry-in, Top-out, Substantial Completion

Productivity Factor - Answer -Production Rates can be affected by multiple factors:
Weather, congested space, area layout, material handling, crew expertise, safety
requirements, complexity

FS (finish to start) - Answer -typical activity relationship

SS (start to start) - Answer -where the start of two activities are tied together.

FF (finish to finish) - Answer -where the finish of two activities are tied together

A logical relationship in which a successor activity cannot finish until a predecessor
activity has finished.

Calendars - Answer -Assigning these to projects ands tasks, defines the working and
non-working days on the project. They can help account for:

Weekends, Holidays, Shifts, Special Events, Weather

Información del documento

Subido en
23 de septiembre de 2025
Número de páginas
7
Escrito en
2025/2026
Tipo
Otro
Personaje
Desconocido
$13.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
GEEKA
3.8
(376)
Vendido
2216
Seguidores
1450
Artículos
62635
Última venta
3 horas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes