Question 1. Which phase of the design process involves gathering
information about client needs and project requirements?
A) Schematic Design
B) Programming
C) Design Development
D) Contract Administration
Answer: B
Explanation: Programming is the phase where information is collected
to understand the client’s needs, goals, and project constraints.
Question 2. What is the main purpose of schematic design in interior
design projects?
A) To finalize construction documents
,NCIDQ Certification Exam
B) To test multiple design concepts and layouts
C) To manage project budgets
D) To select all finishes and furnishings
Answer: B
Explanation: Schematic design explores various layouts and design
options to determine the best solution for the client's needs.
Question 3. Which document legally binds the contractor to complete
work as described for a stated price?
A) Specification
B) Change order
C) Contract
D) Punch list
,NCIDQ Certification Exam
Answer: C
Explanation: A contract is a legally binding agreement outlining the
scope, cost, and terms of construction.
Question 4. Which code primarily addresses accessibility for individuals
with disabilities in the United States?
A) NFPA 101
B) ADA
C) IBC
D) ASTM
Answer: B
Explanation: The Americans with Disabilities Act (ADA) sets standards
for accessible design.
, NCIDQ Certification Exam
Question 5. In project management, which phase directly follows design
development?
A) Programming
B) Contract Administration
C) Construction Documentation
D) Schematic Design
Answer: C
Explanation: After design development, construction documentation is
prepared for bidding and construction.
Question 6. What is the main function of a punch list?
A) To record project expenses
B) To list outstanding items to be completed or corrected before project
closeout