Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Examen

OM 300 Exam 2 Chillcut Questions And Answers With Rationales/Grade A+ Assured

Puntuación
5.0
(2)
Vendido
-
Páginas
34
Grado
A+
Subido en
10-08-2025
Escrito en
2025/2026

OM 300 Exam 2 Chillcut Questions And Answers

Institución
OM 300 Chillcut
Grado
OM 300 Chillcut

Vista previa del contenido

OM 300 Exam 2 Chillcut Questions And Answers

Question 1
Which of the following is NOT one of the three main phases of project management?
A) Planning
B) Scheduling
C) Auditing
D) Controlling
Correct Answer: C) Auditing
Rationale: The three primary phases of project management are Planning (defining the
project), Scheduling (allocating resources and time), and Controlling (monitoring and
correcting). Auditing is a separate function.

Question 2
During which phase of project management are goals set, the project defined, and the team
organized?
A) Planning
B) Scheduling
C) Controlling
D) Executing
Correct Answer: A) Planning
Rationale: The planning phase involves establishing the foundational elements of the
project, including its objectives, scope, work breakdown structure, and organizational
form.

Question 3
Relating people, money, and supplies to specific activities and relating those activities to each
other is the focus of which project management phase?
A) Planning
B) Scheduling
C) Controlling
D) Goal Setting
Correct Answer: B) Scheduling

,Rationale: The scheduling phase is where the timeline is created. It involves sequencing
activities, estimating durations, and allocating the necessary resources to each task.

Question 4
Which project management phase involves monitoring resources, costs, quality, and budgets, and
then revising plans as needed?
A) Planning
B) Scheduling
C) Controlling
D) Organizing
Correct Answer: C) Controlling
Rationale: The controlling phase is the ongoing process of tracking progress against the
plan, identifying variances, and taking corrective action to keep the project on track.

Question 5
A project organization structure is most helpful when:
A) The work is routine and repetitive.
B) The job is unique and somewhat unfamiliar to the existing organization.
C) The tasks are simple and independent.
D) The project has an indefinite timeline.
Correct Answer: B) The job is unique and somewhat unfamiliar to the existing organization.
Rationale: A project-based organization is ideal for unique, temporary endeavors that
require specialized skills and a focused effort that falls outside the normal day-to-day
operations of the company.

Question 6
Which of the following is a primary responsibility of a project manager?
A) Performing all the technical tasks of the project.
B) Ensuring the project comes in within budget and meets quality goals.
C) Securing the initial funding for the project.
D) Reporting directly to the company's shareholders.
Correct Answer: B) Ensuring the project comes in within budget and meets quality goals.

, Rationale: The project manager is ultimately responsible for the successful execution of the
project, which means meeting the triple constraints of time, cost, and quality.

Question 7
Which of the following is an example of an ethical issue a project manager might face?
A) Pressure to alter status reports to mask delays.
B) Being asked to create a detailed project schedule.
C) Receiving a risk mitigation plan from the team.
D) Communicating project goals to the team.
Correct Answer: A) Pressure to alter status reports to mask delays.
Rationale: Project managers can face ethical dilemmas such as being pressured to be
dishonest about project status, compromise quality, or accept inappropriate gifts.

Question 8
Which project scheduling technique is a network diagram that uses a single, deterministic time
estimate for each activity?
A) Gantt Chart
B) Critical Path Method (CPM)
C) Program Evaluation and Review Technique (PERT)
D) Factor-Rating Method
Correct Answer: B) Critical Path Method (CPM)
Rationale: CPM is a network-based technique that uses one specific time estimate for each
activity to determine the project's critical path and duration.

Question 9
What is the first step in both the PERT and CPM project management techniques?
A) Draw the network diagram.
B) Compute the critical path.
C) Define the project and prepare the work breakdown structure.
D) Assign time estimates to each activity.
Correct Answer: C) Define the project and prepare the work breakdown structure.
Rationale: Before any scheduling or analysis can occur, the project's scope must be clearly
defined and broken down into smaller, manageable work packages or activities.

Escuela, estudio y materia

Institución
OM 300 Chillcut
Grado
OM 300 Chillcut

Información del documento

Subido en
10 de agosto de 2025
Archivo actualizado en
29 de octubre de 2025
Número de páginas
34
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$21.49
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Reseñas de compradores verificados

Se muestran los 2 comentarios
10 meses hace

10 meses hace

5.0

2 reseñas

5
2
4
0
3
0
2
0
1
0
Reseñas confiables sobre Stuvia

Todas las reseñas las realizan usuarios reales de Stuvia después de compras verificadas.

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
DICKENS maryland university
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
2304
Miembro desde
1 año
Número de seguidores
6
Documentos
2130
Última venta
1 semana hace
PROSTUDYHUB

4.9

988 reseñas

5
870
4
101
3
12
2
4
1
1

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes