If the frequency bias setting B) The ACE will be a negative value and AGC will increase
is set to a less negative generation
value than the frequency
response of a Balancing
Authority and a
frequency increase is
caused by a sudden loss of
load in an external
balancing area, what will
be the result?
A) The ACE will be zero
and will take no AGC
action
B) The ACE will be a
negative value and AGC
will increase generation
C) The ACE will be a
positive value and AGC
will lower generation
D) This will not affect the ACE
1/137
,7/29/25, 12:32 AM SOS NERC Prep - RElIABILITY Exam 2025 Questions and Verified Answers
If the frequency bias setting C) The ACE will be a positive value and AGC will lower
is less negative than the generation.
frequency response of a
Balancing Authority and a
frequency decline is
caused by a sudden loss of
generation in an external
balancing area, what will be
the result?
A) The ACE will be a
negative value and AGC
will increase
generation.
B) This will not affect the ACE.
C) The ACE will be a
positive value and AGC
will lower generation.
D) The ACE will be zero
and will take no AGC
action.
It is the responsibility of A) Transmission Operators and Balancing Authorities
which entity/entities to
develop, maintain, and
implement load shedding
plans?
A) Transmission Operators
and Balancing Authorities
B) Reliability Coordinator
C) Load Serving Entities
D) Balancing Authority
2/137
,7/29/25, 12:32 AM SOS NERC Prep - RElIABILITY Exam 2025 Questions and Verified Answers
A Transmission line is loaded D) Initiate the restoration of the parallel line.
25% above its SOL. A
parallel line is out for
routine
maintenance and can be
placed in service in 10
minutes. What is the first
step the
Operator should take to
reduce the line loading?
A) Shed load at the
downstream bus.
B) Open the line.
C) Re-Dispatch Generation.
D) Initiate the restoration
of the parallel line.
As a Transmission Operator, D) All answers are correct
you realize that the voltage
level is starting to decline in
the North West part of the
system. Which of the
following devices should
you, as a Transmission
Operator, be able to
operate, and/or have
another entity operate to
raise the voltage level back
to normal in the North
West part of the system?
A) Transformer Underload Tap
Changers
B) Shunt Capacitor Banks
C) Generator Reactive Output
3/137
, 7/29/25, 12:32 AM SOS NERC Prep - RElIABILITY Exam 2025 Questions and Verified Answers
D) All answers are correct
Voltage reduction for load A) Distribution system
relief should be made on
the _________.
A) Distribution system
B) Entire Interconnection
simultaneously
C) Tie-lines with other
Balancing Authority Areas
D) Transmission System
Under Frequency Load D) Shedding load prior to generation tripping
Shedding (UFLS) is to
stabilize the imbalance
between
generation and load that has
been created by a system
disturbance. This is
accomplished by _.
A) Tripping generation first
B) Voltage reduction on the
distribution system.
C) Shedding all load to arrest
frequency
D) Shedding load prior
to generation tripping
4/137