100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

SUBGRADE & BASE INSPECTION – FDOT EXAM QUESTIONS WITH COMPLETE SOLUTIONS

Puntuación
-
Vendido
-
Páginas
13
Grado
A+
Subido en
06-07-2025
Escrito en
2024/2025

SUBGRADE & BASE INSPECTION – FDOT EXAM QUESTIONS WITH COMPLETE SOLUTIONS

Institución
FDOT
Grado
FDOT









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
FDOT
Grado
FDOT

Información del documento

Subido en
6 de julio de 2025
Número de páginas
13
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

SUBGRADE & BASE INSPECTION –
FDOT EXAM QUESTIONS WITH
COMPLETE SOLUTIONS
What is the time limit for placement of the central-plant mixture in adjacent passes? -
Answer-30 minutes

Is the dumping of soil-cement mixtures in piles or windrows on the subgrade
acceptable? - Answer-No

What should you use to check the depth of cement-treated subgrades? - Answer--
Smooth metal rod
-Jack
-Stringline

What tool should you use in checking for uniformity of mixing - Answer-Posthole digger

In a mixed, cement-treated subgrade, there should be no soil particles larger than __ -
Answer-1'' in diameter

For cement-treated subgrades, where are the maximum density and optimum moisture
values determined?

Who makes these determinations? - Answer--In the field

-Inspector

When is the earliest that compaction can be started after mixing has been completed?
___ When is the latest? ___ - Answer-Immediately; Not later than 60 minutes

Cement-treated subgrades must be compacted to at least __ percent of the maximum
density. - Answer-95

Areas of the subgrade that need additional soil-cement mixture in order to comply with
the plans must first be lightly __. - Answer-Scarified

Should cement-treated subgrade surface higher or lower from plan grade to be
corrected? - Answer-Yes

Cement-treated subgrades of up to 6-inch specified thickness must not have thickness
deficiencies greater than __ - Answer-1/2 inch

, How is moisture retained in the subgrade BEFORE asphalt is applied? - Answer-By
sprinkling

How long is the curing period? (Cement treated subgrades) - Answer-7 days

What three things should you verify during curing coat application? - Answer--
Application at a specified rate
-Complete uniform coverage
-Sanding of asphaltic material with acceptable aggregate

How many different kinds of base courses are included in the Standard Specifications? -
Answer-9

The purpose of a base course is to __. - Answer-Support the pavement

For tangent sections, the maximum interval for setting the stakes along the roadway is
__ feet. - Answer-50

Generally, grade stakes are offset __ feet from the edge of mixing operations. - Answer-
3

Are blue tops sometimes set after the base material is placed and balanced? - Answer-
Yes

Sometimes blue tops are covered by the construction operations. Why must they be
uncovered? - Answer-So that the motor grader operator can clip over the top

If you are to be the Base Inspector and did not inspect the subgrade operations, should
you assume the subgrade meets all the requirements? - Answer-No

Must spongy areas and ruts in the subgrade be corrected BEFORE the beginning of
base course operations? - Answer-Yes

Do the contract plans govern over the special provisions? - Answer-No

List three general requirements for all equipment used in subgrade operations: -
Answer--Be in good condition
-Operate safely
-Produce desired results

How are spread distances marked? - Answer-Stakes

A certain transport holds 42,360 pounds of cement. The design application rate is 30
pounds. The subgrade is 21 feet wide. What is the spread distance for this particular
transport? __ (to the nearest foot) - Answer-605 feet
$21.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
biggdreamer Havard School
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
250
Miembro desde
2 año
Número de seguidores
68
Documentos
18071
Última venta
1 semana hace

4.0

38 reseñas

5
22
4
4
3
6
2
2
1
4

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes