Project Management: Activity-on-Node Diagram Construction and Analysis
To create an Activity-on-Node (AON) diagram for the original project and the project with the
new activity, we need to understand the dependencies between the activities and the estimated
durations. Based on the provided information, we can construct the AON diagrams as follows:
AON for the original project:
1.1.1.1 (5d)
|
V
1.2.0.1 (5d)
/ \
V V
1.2.1.1 (3d) 1.2.2.1 (6d)
| /
V V
1.2.3.1 (2d)
|
V
1.2.3.2 (3d)
/ \
V V
1.2.3.3 (3d) 1.2.3.4 (3d)
|
V
1.3.1.1 (5d)
|
V
1.4.1.1 (1d)
AON including the new activity (PenTesting):
1.1.1.1 (5d)
|
V
1.2.0.1 (5d)
/ \
V V
1.2.1.1 (3d) 1.2.2.1 (6d)
| /