Page | 1
ICC VAPOR RECOVERY 2 2025 BRAND
NEW ACTUAL EXAM WITH ANSWERS.
According to Executive Order VR-201-A, a pressure/vacuum
(P/V) vent valve shall be secured with a torque setting between
____ ft. lbs.
a. 10-20
b. 20-50
c. 50-75
d. 75-100 -correct answer -b. 20-50
When installing a Healy VP-1000 Vac-Motors, a technician should
do all of the following EXCEPT:
a. replace the nozzle
b. wear eye protection
c. properly barricade the area
d. turn off power to the dispenser -correct answer -a. replace the
nozzle
, Page | 2
The clean air separator is a component of the:
a. OPW phase I EVR
b. Phil-Tite Phase I EVR
c. Healy EVR Phase II EVR
d. OPW Vapor Saver -correct answer -c. Healy EVR Phase II
EVR
According to Healy Executive Order VR-201-A Vapor Recovery
Repair Records are to be maintained by the:
a. local air district
b. repair contractor
c. testing contractor
d. gasoline dispensing facility (GDF) operator -correct answer -d.
gasoline dispensing facility (GDF) operator
According to Executive Order VR-201-A, if the dispensing vacuum
of the Healy VP-1000 pump is below ____ inches of water
column, the dispenser should be removed from service.
a. 50
, Page | 3
b. 60
c. 75
d. 100 -correct answer -b. 60
According to the Vapor Recovery Defects List (VRED), the ____
of any component required to be used by the system's Executive
Order is not considered a defect.
a. absence
b. disconnection
c. proper installation
d. improper installation -correct answer -c. proper installation
According to CP-201, liquid traps in the dispenser vapor piping
are:
a. not allowed
b. allowed only with an assist system
c. allowed if approved by the Phase II system manufacturer
d. allowed when hoses with liquid removal systems are used -
correct answer -a. not allowed
ICC VAPOR RECOVERY 2 2025 BRAND
NEW ACTUAL EXAM WITH ANSWERS.
According to Executive Order VR-201-A, a pressure/vacuum
(P/V) vent valve shall be secured with a torque setting between
____ ft. lbs.
a. 10-20
b. 20-50
c. 50-75
d. 75-100 -correct answer -b. 20-50
When installing a Healy VP-1000 Vac-Motors, a technician should
do all of the following EXCEPT:
a. replace the nozzle
b. wear eye protection
c. properly barricade the area
d. turn off power to the dispenser -correct answer -a. replace the
nozzle
, Page | 2
The clean air separator is a component of the:
a. OPW phase I EVR
b. Phil-Tite Phase I EVR
c. Healy EVR Phase II EVR
d. OPW Vapor Saver -correct answer -c. Healy EVR Phase II
EVR
According to Healy Executive Order VR-201-A Vapor Recovery
Repair Records are to be maintained by the:
a. local air district
b. repair contractor
c. testing contractor
d. gasoline dispensing facility (GDF) operator -correct answer -d.
gasoline dispensing facility (GDF) operator
According to Executive Order VR-201-A, if the dispensing vacuum
of the Healy VP-1000 pump is below ____ inches of water
column, the dispenser should be removed from service.
a. 50
, Page | 3
b. 60
c. 75
d. 100 -correct answer -b. 60
According to the Vapor Recovery Defects List (VRED), the ____
of any component required to be used by the system's Executive
Order is not considered a defect.
a. absence
b. disconnection
c. proper installation
d. improper installation -correct answer -c. proper installation
According to CP-201, liquid traps in the dispenser vapor piping
are:
a. not allowed
b. allowed only with an assist system
c. allowed if approved by the Phase II system manufacturer
d. allowed when hoses with liquid removal systems are used -
correct answer -a. not allowed