What organizational process assets are updated as part of the Close Project or Process Phase?
- CORRECT ANSWER Lessons Learned Repository
Project Resource Management processes best defines the process of tracking team member
performance, providing feedback, resolving issues, and managing team changes. -
CORRECT ANSWER Manage Team
How many process groups belong to the Executing Process Group? - CORRECT
ANSWER 10
Which of the following is a tool and technique to the Plan Schedule Management -
CORRECT ANSWER Alternative Analysis
In agile/adaptive environments, who determine how plans and components should integrate?
- CORRECT ANSWER Team Members
Which of the following about Manage Stakeholder Engagement are true EXCEPT: -
CORRECT ANSWER The ability of stakeholders to influence the project is typically
lowest during the stages and gets progressively higher as the project progresses
Assumption logs and input logs are inputs to which Project Integration Management process?
- CORRECT ANSWER Monitor and Control Project Work
What is the output of Direct and Manage Project Work? - CORRECT
ANSWER Deliverables
, Iterative and agile practices promote the engagement of _______ ________ as local domain
experts in Project Integration Management - CORRECT ANSWER Team Members
Which of the following is an input to the Plan Schedule Management Process? - CORRECT
ANSWER Scope Management Plan
The process of formalizing acceptance of the completed project is which project management
process associate with the Project Scope Management Knowledge Area? - CORRECT
ANSWER Validate Scope
In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates
that the project team has decided - CORRECT ANSWER Not to change the project
management plan to deal with a risk, or is unable to identify any other suitable response
strategy
1Which of the following are examples of subsidiary management plan components in the
project management plan? - CORRECT ANSWER Scope Management Plan and
Quality Management Plan
As the project manager, which of the following is your responsibility as part of the
Monitoring and Controlling Process Group? - CORRECT ANSWER Continuously
monitor the work being completed
Your earned value management analysis indicates that your project is falling behind its
baseline schedule. You know this because the cumulative EV is much: - CORRECT
ANSWER Lower than the cumulative PV
What is the output of the Estimate Costs process? - CORRECT ANSWER Basis of
estimates
Project managers are similar to conductors of a large orchestra because they perform which
of the following similar roles? - CORRECT ANSWER They are responsible for the
team, and integrate multiple disciplines