1. What is the primary responsibility of a Texas state agency’s Contract Developer during
the solicitation process?
A. Negotiating contracts with vendors
B. Ensuring payments are made on time
C. Developing clear and complete solicitation documents
D. Auditing the procurement records
Correct Answer: C. Developing clear and complete solicitation documents
Explanation: The Contract Developer's main role is to ensure that solicitation documents are
complete, clear, and compliant with state requirements, including clearly defined scopes,
evaluation criteria, and terms.
2. Which procurement method is most appropriate for acquiring complex services where
price is not the sole determining factor?
A. Invitation for Bids (IFB)
B. Request for Qualifications (RFQ)
C. Request for Proposals (RFP)
D. Request for Information (RFI)
Correct Answer: C. Request for Proposals (RFP)
Explanation: An RFP is used when the best value is determined by multiple factors, not just
price. It allows for evaluation based on qualifications, experience, and proposed methods.
,3. When must a state agency submit a solicitation to the Contract Advisory Team (CAT)
for review?
A. When it involves an emergency procurement
B. For solicitations with an estimated value of $5 million or more
C. For every IT contract regardless of value
D. Only when directed by the procurement director
Correct Answer: B. For solicitations with an estimated value of $5 million or more
Explanation: The CAT review is mandated for solicitations of $5 million or more (unless
exempt), ensuring proper oversight and compliance with best practices.
4. What is the purpose of the Historically Underutilized Business (HUB) Program in Texas
procurements?
A. To award all contracts to minority vendors
B. To provide loans to HUBs
C. To increase contracting opportunities for HUBs
D. To enforce mandatory awards to local businesses
Correct Answer: C. To increase contracting opportunities for HUBs
Explanation: The HUB Program promotes full and equal opportunities for minority-, women-,
and service-disabled veteran-owned businesses in state contracting.
5. What document formally initiates a contract and binds the parties?
A. Solicitation document
B. Purchase order
C. Award letter
D. Executed contract
Correct Answer: D. Executed contract
Explanation: Only an executed contract, signed by all authorized parties, legally binds them to
the agreed terms.
6. Which of the following is considered a best practice during contract development?
A. Reusing prior contracts without review
B. Including vague terms to allow flexibility
C. Drafting a clear scope of work (SOW)
D. Letting vendors define the deliverables
Correct Answer: C. Drafting a clear scope of work (SOW)
Explanation: A detailed and unambiguous SOW sets expectations, minimizes disputes, and
supports successful contract performance.
, 7. What is the primary role of the Statewide Procurement Division (SPD)?
A. Approving payments over $1 million
B. Monitoring vendors' tax compliance
C. Establishing and overseeing procurement policies
D. Representing vendors in state contract negotiations
Correct Answer: C. Establishing and overseeing procurement policies
Explanation: SPD manages the procurement policies, provides training (e.g., CTCD/CTCM),
and ensures uniformity across agencies.
8. Which is true regarding contract amendments?
A. They must be informal and verbal
B. They are only necessary if the vendor requests them
C. They must be documented and signed by authorized representatives
D. They are unnecessary if the change is under $5,000
Correct Answer: C. They must be documented and signed by authorized representatives
Explanation: All contract changes must be formally documented to maintain legality and
accountability.
1. What is the primary purpose of the procurement planning phase?
Answer: A. To determine the procurement strategy
Explanation: Planning ensures the correct method and strategy are used to achieve best
value.
2. What is a requirement for all solicitations over $25,000?
Answer: B. Posting on the Electronic State Business Daily (ESBD)
Explanation: State law mandates posting procurements over $25,000 on the ESBD for
transparency.
3. When must a HUB Subcontracting Plan (HSP) be submitted?
Answer: A. For contracts of $100,000 or more
Explanation: The HSP is required to ensure HUB participation for contracts ≥
$100,000.
Developer (CTCD) Exam
Questions And Verified
Answers With Explanations
1. What is the primary responsibility of a Texas state agency’s Contract Developer during
the solicitation process?
A. Negotiating contracts with vendors
B. Ensuring payments are made on time
C. Developing clear and complete solicitation documents
D. Auditing the procurement records
Correct Answer: C. Developing clear and complete solicitation documents
Explanation: The Contract Developer's main role is to ensure that solicitation documents are
complete, clear, and compliant with state requirements, including clearly defined scopes,
evaluation criteria, and terms.
2. Which procurement method is most appropriate for acquiring complex services where
price is not the sole determining factor?
A. Invitation for Bids (IFB)
B. Request for Qualifications (RFQ)
C. Request for Proposals (RFP)
D. Request for Information (RFI)
Correct Answer: C. Request for Proposals (RFP)
Explanation: An RFP is used when the best value is determined by multiple factors, not just
price. It allows for evaluation based on qualifications, experience, and proposed methods.
,3. When must a state agency submit a solicitation to the Contract Advisory Team (CAT)
for review?
A. When it involves an emergency procurement
B. For solicitations with an estimated value of $5 million or more
C. For every IT contract regardless of value
D. Only when directed by the procurement director
Correct Answer: B. For solicitations with an estimated value of $5 million or more
Explanation: The CAT review is mandated for solicitations of $5 million or more (unless
exempt), ensuring proper oversight and compliance with best practices.
4. What is the purpose of the Historically Underutilized Business (HUB) Program in Texas
procurements?
A. To award all contracts to minority vendors
B. To provide loans to HUBs
C. To increase contracting opportunities for HUBs
D. To enforce mandatory awards to local businesses
Correct Answer: C. To increase contracting opportunities for HUBs
Explanation: The HUB Program promotes full and equal opportunities for minority-, women-,
and service-disabled veteran-owned businesses in state contracting.
5. What document formally initiates a contract and binds the parties?
A. Solicitation document
B. Purchase order
C. Award letter
D. Executed contract
Correct Answer: D. Executed contract
Explanation: Only an executed contract, signed by all authorized parties, legally binds them to
the agreed terms.
6. Which of the following is considered a best practice during contract development?
A. Reusing prior contracts without review
B. Including vague terms to allow flexibility
C. Drafting a clear scope of work (SOW)
D. Letting vendors define the deliverables
Correct Answer: C. Drafting a clear scope of work (SOW)
Explanation: A detailed and unambiguous SOW sets expectations, minimizes disputes, and
supports successful contract performance.
, 7. What is the primary role of the Statewide Procurement Division (SPD)?
A. Approving payments over $1 million
B. Monitoring vendors' tax compliance
C. Establishing and overseeing procurement policies
D. Representing vendors in state contract negotiations
Correct Answer: C. Establishing and overseeing procurement policies
Explanation: SPD manages the procurement policies, provides training (e.g., CTCD/CTCM),
and ensures uniformity across agencies.
8. Which is true regarding contract amendments?
A. They must be informal and verbal
B. They are only necessary if the vendor requests them
C. They must be documented and signed by authorized representatives
D. They are unnecessary if the change is under $5,000
Correct Answer: C. They must be documented and signed by authorized representatives
Explanation: All contract changes must be formally documented to maintain legality and
accountability.
1. What is the primary purpose of the procurement planning phase?
Answer: A. To determine the procurement strategy
Explanation: Planning ensures the correct method and strategy are used to achieve best
value.
2. What is a requirement for all solicitations over $25,000?
Answer: B. Posting on the Electronic State Business Daily (ESBD)
Explanation: State law mandates posting procurements over $25,000 on the ESBD for
transparency.
3. When must a HUB Subcontracting Plan (HSP) be submitted?
Answer: A. For contracts of $100,000 or more
Explanation: The HSP is required to ensure HUB participation for contracts ≥
$100,000.