APM PFQ Exam Questions With correct Answers

Puntuación
-
Vendido
-
Páginas
86
Grado
A+
Subido en
23-04-2025
Escrito en
2024/2025

APM PFQ Exam Questions With correct Answers

Institución
APM
Grado
APM











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
APM
Grado
APM

Información del documento

Subido en
23 de abril de 2025
Número de páginas
86
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

APM PFQ Exam Questions With correct
Answers

Which of the following is not a stage in an issue resolution process?

a. Share the issue with stakeholders.

b. Track the issue to closure. c. Escalate to the sponsor.

d. Apply change control. - correct answersA



Which of the following are challenges for a project manager developing and leading a project
team?

1) Issues and incompatibility amongst team members

2) Getting the right skills and attributes amongst team members

3) Co-location of team members in the same geographic area

4) Lack of accountability of team members

a. 1, 2 & 3

b. 1, 2 & 4

c. 1, 3 & 4

d. 2, 3 & 4 - correct answersC



Which of the following is an activity in a typical change control process?

a. Recommendation.

b. Justification.

c. Planning.

d. Continuous improvement - correct answersA

,The purpose of quality assurance is to:

a. provide confidence the project will satisfy the relevant quality standards.

b. determine a set of procedures and standards for project management.

c. inspect, measure and test deliverables and processes.

d. define the scope and specifics of a project's deliverables - correct answersA



A project manager might use a PESTLE analysis in order to:

a. mitigate all possible risks to the project.

b. identify and mitigate factors that may affect the project.

c. control technological change during the project.

d. consider team social roles in early stages of the project - correct answersB



Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3)
Deployment 4) Development

a. 3 and 4 only

b. 1, 2 and 3

c. 1 and 2 only

d. 2, 3 and 4 - correct answersD



Which of the following is the responsibility of a project manager?

a. Ensuring a project is aligned to the organisation's strategy.

b. Focusing on project benefits and aligning priorities.

c. Achieving the project's success criteria.

d. Improving process, tools and techniques used in a project - correct answersC



To develop and establish a proper communication plan within a project, the project manager
needs to consider which type of analysis?

,a. Budget.

b. Stakeholder.

c. Resource.

d. Schedule - correct answersB



Which of the following is a responsibility of the project sponsor?

a. Creating a project cost breakdown structure.

b. Authoring the project management plan.

c. Creating a project work breakdown structure.

d. Owning the project business case. - correct answersD



Portfolio management includes prioritising:

a. projects and/or programmes that contribute directly to the organisation's strategic
objectives.

b. projects with exceptionally high returns on investment.

c. projects and programmes over business as usual.

d. projects which maximise change over those which maximise investment - correct answersA



Which of the following actions would not help a team leader influence the performance of
their team?

a. Creating an exclusive environment.

b. Providing clear roles and responsibilities.

c. Promoting openness and honesty.

d. Developing a trusting relationship. - correct answersA



One difference between a project and business as usual is:

a. projects achieve specified benefits but business as usual has only vague benefits.

, b. projects drive change whereas business as usual continues existing activities.

c. projects have tightly controlled budgets whereas business as usual does not.

d. projects have unclear deadlines but business as usual has multiple milestones - correct
answersB



The purpose of project progress reporting is to:

a. ensure a simpler critical path.

b. enable the tracking of project deliverables.

c. ensure stakeholder acceptance of project deliverables.

d. provide an increased total float. - correct answersB



Which of the following is the purpose of an estimating funnel?

a. Keeping resource usage to a minimum to help reduce costs.

b. Supporting the production of comparative estimates.

c. Identifying where costs can be minimised when preparing a budget.

d. Representing increasing levels of estimating accuracy achieved through the life cycle -
correct answersD



One advantage of virtual communications is:

a. that nonverbal signals can have an impact on discussions.

b. it's easy to detect signs of conflict within the project team.

c. access to a wider resource pool for the project.

d. that the project team will always be co-located. - correct answersC



Which technique could be used by a project manager when resources are limited?

a. Resource aggregation.

b. Resource estimation.
$19.49
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Thumbnail
Package deal
APM bundled Exams
-
11 2025
$ 185.89 Más información

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
SMARTPRO Howard Community College
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
22
Miembro desde
9 meses
Número de seguidores
0
Documentos
6185
Última venta
1 semana hace

Welcome to your reliable partner for academic achievement. My page is built on one principle: providing the shortest, clearest path to mastery and confidence. I create high-impact resources designed to turn your study hours into top performance, offering expert Study Guides (concise notes that simplify challenging concepts) and strategic Revision Papers (realistic practice questions that maximize your score potential). Success is a strategy. Stop wading through endless readings and start using proven tools to guarantee your best possible outcome. All the best.

Lee mas Leer menos
4.0

4 reseñas

5
2
4
0
3
2
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes