Walmart SWPPP Exam Questions And Answers
|Latest 2025 | Guaranteed Pass
The Clean Water Act - (answers)The 1970s federal law that set into place the
regulation of stormwater.
NPDES - (answers)Requirements for managing storm water activity on a
construction site.
The Notice of Termination (NOT) can be filed when - (answers)All construction
activity (inside and outside) is complete and permanent stabilization has been
verified as adequate to meet permit requirements.
All of the following must occur before construction starts, except:
1. Prepare the SWPPP
2. Determine the Operator(s)
3. Submit the Notice of Intent (NOI)
4. Submit the Notice of Termination (NOT) - (answers)4. Submit the Notice of
Termination (NOT).
Which of the following is NOT a beneficial use of water?
1. Swimming
2. Drinking
3. Flushing a spill down a storm drain
, 2
4. Industrial and agricultural water supply - (answers)3. Flushing a spill down a
storm drain.
When installing and maintaining a check dam, make sure:
1. Stormwater is directed around the check dam
2. Void spaces are filled with sediment
3. The low point (overflow) of the check dam is in the middle of the channel
4. The high point of the check dam is in the middle of the channel - (answers)3.
The low point (overflow) of the check dam is in the middle of the channel.
To reduce the possibility of undercutting in channels, you should:
1. Stabilize diversions and swales within 21-days of construction
2. Add mulch and straw
3. Install filter fabric under rock and similar materials placed within the
stormwater conveyance
4. Never install a BMP in a stormwater conveyance - (answers)3. Install filter
fabric under rock and similar materials placed within the stormwater conveyance.
The Good Housekeeping section of the SWPPP must include all BUT which of the
following:
1. Hazardous Waste Management and Disposal Procedures
2. Solid Waste Management and Disposal Procedures
3. Sanitary Waste Management and Disposal Procedures
Walmart SWPPP Exam Questions And Answers
|Latest 2025 | Guaranteed Pass
The Clean Water Act - (answers)The 1970s federal law that set into place the
regulation of stormwater.
NPDES - (answers)Requirements for managing storm water activity on a
construction site.
The Notice of Termination (NOT) can be filed when - (answers)All construction
activity (inside and outside) is complete and permanent stabilization has been
verified as adequate to meet permit requirements.
All of the following must occur before construction starts, except:
1. Prepare the SWPPP
2. Determine the Operator(s)
3. Submit the Notice of Intent (NOI)
4. Submit the Notice of Termination (NOT) - (answers)4. Submit the Notice of
Termination (NOT).
Which of the following is NOT a beneficial use of water?
1. Swimming
2. Drinking
3. Flushing a spill down a storm drain
, 2
4. Industrial and agricultural water supply - (answers)3. Flushing a spill down a
storm drain.
When installing and maintaining a check dam, make sure:
1. Stormwater is directed around the check dam
2. Void spaces are filled with sediment
3. The low point (overflow) of the check dam is in the middle of the channel
4. The high point of the check dam is in the middle of the channel - (answers)3.
The low point (overflow) of the check dam is in the middle of the channel.
To reduce the possibility of undercutting in channels, you should:
1. Stabilize diversions and swales within 21-days of construction
2. Add mulch and straw
3. Install filter fabric under rock and similar materials placed within the
stormwater conveyance
4. Never install a BMP in a stormwater conveyance - (answers)3. Install filter
fabric under rock and similar materials placed within the stormwater conveyance.
The Good Housekeeping section of the SWPPP must include all BUT which of the
following:
1. Hazardous Waste Management and Disposal Procedures
2. Solid Waste Management and Disposal Procedures
3. Sanitary Waste Management and Disposal Procedures