• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 2 fuera de 15 páginas
Examen

CCCA Exam Questions and Answers Latest Update 2025 Fully Solved

Document preview thumbnail
Vista previa 2 fuera de 15 páginas

CCCA Exam Questions and Answers Latest Update 2025 Fully Solved Preliminary Project Description PPD - Answers describes the scope and relationships of major elements organized in terms of building systems and components - CSI recommends UniFormat for PPDS - describes as a system of components Outline specifications - Answers an abbreviated set of specification requirements normally included with schematic design or design development documents. Bassi for revising estimates of cost/schedule value - Record decisions shop drawing - Answers not a contract document - repared by contractor / sub/equipment supplier and show how an aspect of the work is to be fabricated and installed methods of specifying - Answers Descriptive, performance, reference standards, proprietary Descriptive Specification - Answers detailed description of required properties of product. A/E responsible for determination of desired performance criteria Performance Specifications - Answers required result with criteria for verifying compliance Proprietary specifications - Answers identify the desired manufacture or unique characteristic closed vs open proprietary specification - Answers Two types of bonds - Answers performance bond and payment bond When are bonds expected to be delievered? - Answers To the owner when the contractor delivers the executed owner-contractor agreements What are bonds - Answers They are not insurance What protects the owner against mechanics liens? - Answers Payment bond What protects suppliers and subs against nonpayment? - Answers Payment bond Surety bond - Answers AKA contract bond Performance Bond - Answers guaranty that if the contractor fails to perform, the surety will either complete the contract or provide sufficient funds up to the penalty sum for such completion Other bonds in addition to performance and payment bonds - Answers maintenance bonds, lien bonds, retainage bonds (alternative to retainage), license and permit bonds (from AHJs) Who is responsible for coordinating work to be completed under separate contracts? - Answers Owner Preliminary schedules must be submitted at least 10 days after the effective date of the contract - Answers According to many general standard conditions - ConsensusDocs doesn't have this requirement Two most frequently used schedule formats - Answers critical path method (CPM) bar chart Approval for schedule by contractor - Answers A/E reviews for compliance with contracts - Owner determines if it meets requirements - In some contracts, schedule revisions are allowed only by change order Comprehensive schedule AKA project schedule - Answers often a critical path schedule beginning with the inception of the project and concludes with final acceptance schedule of values - Answers complements the progress schedule identifies how all the costs int he project are apportioned A/E can request supporting documentation from contractor when thee is a disagreement on the proportionate value of items of work Change orders are usually added to schedule of values What records does the A/E maintain? - Answers field observation reports documentation of non-confirming work correspondence meeting minutes communication reports submittals test reports payment requests and certifications schedule requests for interpretation, clarification or information proposal requests or change order requests contract document modifications

Vista previa del contenido

CCCA Exam Questions and Answers Latest Update 2025 Fully Solved

Preliminary Project Description PPD - Answers describes the scope and relationships of major elements
organized in terms of building systems and components - CSI recommends UniFormat for PPDS -
describes as a system of components

Outline specifications - Answers an abbreviated set of specification requirements normally included with
schematic design or design development documents. Bassi for revising estimates of cost/schedule value
- Record decisions

shop drawing - Answers not a contract document - repared by contractor / sub/equipment supplier and
show how an aspect of the work is to be fabricated and installed

methods of specifying - Answers Descriptive, performance, reference standards, proprietary

Descriptive Specification - Answers detailed description of required properties of product. A/E
responsible for determination of desired performance criteria

Performance Specifications - Answers required result with criteria for verifying compliance

Proprietary specifications - Answers identify the desired manufacture or unique characteristic

closed vs open proprietary specification - Answers

Two types of bonds - Answers performance bond and payment bond

When are bonds expected to be delievered? - Answers To the owner when the contractor delivers the
executed owner-contractor agreements

What are bonds - Answers They are not insurance

What protects the owner against mechanics liens? - Answers Payment bond

What protects suppliers and subs against nonpayment? - Answers Payment bond

Surety bond - Answers AKA contract bond

Performance Bond - Answers guaranty that if the contractor fails to perform, the surety will either
complete the contract or provide sufficient funds up to the penalty sum for such completion

Other bonds in addition to performance and payment bonds - Answers maintenance bonds, lien bonds,
retainage bonds (alternative to retainage), license and permit bonds (from AHJs)

Who is responsible for coordinating work to be completed under separate contracts? - Answers Owner

Preliminary schedules must be submitted at least 10 days after the effective date of the contract -
Answers According to many general standard conditions - ConsensusDocs doesn't have this requirement

, Two most frequently used schedule formats - Answers critical path method (CPM)

bar chart

Approval for schedule by contractor - Answers A/E reviews for compliance with contracts - Owner
determines if it meets requirements - In some contracts, schedule revisions are allowed only by change
order

Comprehensive schedule AKA project schedule - Answers often a critical path schedule beginning with
the inception of the project and concludes with final acceptance

schedule of values - Answers complements the progress schedule

identifies how all the costs int he project are apportioned



A/E can request supporting documentation from contractor when thee is a disagreement on the
proportionate value of items of work



Change orders are usually added to schedule of values

What records does the A/E maintain? - Answers field observation reports

documentation of non-confirming work

correspondence

meeting minutes

communication reports

submittals

test reports

payment requests and certifications

schedule

requests for interpretation, clarification or information

proposal requests or change order requests

contract document modifications

Submittal Log - Answers should be maintained by both the A/E and contractor

Información del documento

Subido en
10 de abril de 2025
Número de páginas
15
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$10.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TutorJosh
3.5
(77)
Vendido
508
Seguidores
16
Artículos
33081
Última venta
5 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes