An RFP for the lease of an obsolete tower on the airport closed last week. The
solicitation listed the criteria for selection in order of importance. Fixed weights were
assigned to each criterion. The weights were not disclosed in the RFP. The Evaluation
Committee received the project and began their evaluation. Several members of the
committee immediately brought forth the concerns that 1) the first criterion was not the
most important and should have been listed under the next one and 2) the fixed weight
scoring should likewise be adjusted. The committee chair stated that the criteria could
not be changed. Why?
A. The chair was instrumental in creating the list of importance and the assigned weights.
,B. The committee cannot change the evaluation criteria in the RFP
C. The list of importance favored a preferred vendor.
D. The fixed weight scoring method did not fit the situation and variable weights should
have been used.
Give this one a try later!
B. The committee cannot change the evaluation criteria in the RFP
Having received a requisition from the using department to establish a term contract for
goods or services, the best way to begin putting that contract together is with
________________.
A. The end result in mind
B. A detailed specification or scope of work from the NIGP library
C. A similar contract from another agency
D. The boiler-plate of terms and conditions previously reviewed and approved by the
legal department.
Give this one a try later!
A. The end result in mind
The consideration of essential functions, delegations of authority, vital records
management and human capital is part of:
A. Contract administration planning
B. Continuity of operations planning
C. Major procurement planning
D. Staff reorganization planning
Give this one a try later!
, B. Continuity of operations planning
Why is the Request for Proposal (RFP) process often perceived as problematic by an
agency's leadership?
A. The award decision is very quantifiable.
B. The award decision is based on qualitative variables.
C. The price is rarely known on award.
D. The outcome of the RFP process is difficult to justify.
Give this one a try later!
B. The award decision is based on qualitative variables.
After assuming her new duties as a procurement manager, Janet discovers that the
policies and procedures need revising. For the best examples of policies, procedures,
forms, documents and other materials, she should obtain a copy of:
A. The Model Procurement Code
B. The Uniform Commercial Code
C. Her agency's code enforcement manual
D. Her state's statutes
Give this one a try later!
A. The Model Procurement Code
, An organization's mission statement should:
A. Express the organization's purpose for existence
B. Identify how the organization wants to function in the future
C. Articulate the goals and objectives of the organization
D. Communicate particular strategies for success
Give this one a try later!
A. Express the organization's purpose for existence
Which guideline describes how a procurement official should proceed when an award
protest is filed?
A. Always delay start of the project.
B. Always start the project since time is of the essence.
C. Decide whether or not to start the project after consulting legal counsel.
D. Seek a judicial decision
Give this one a try later!
C. Decide whether or not to start the project after consulting legal counsel
Constructive suspensions occur when a public agency is found to be responsible for a
work stoppage and yet they did not actually issue a suspension of work to the
contractor. There are seven examples noted in the literature
Give this one a try later!
solicitation listed the criteria for selection in order of importance. Fixed weights were
assigned to each criterion. The weights were not disclosed in the RFP. The Evaluation
Committee received the project and began their evaluation. Several members of the
committee immediately brought forth the concerns that 1) the first criterion was not the
most important and should have been listed under the next one and 2) the fixed weight
scoring should likewise be adjusted. The committee chair stated that the criteria could
not be changed. Why?
A. The chair was instrumental in creating the list of importance and the assigned weights.
,B. The committee cannot change the evaluation criteria in the RFP
C. The list of importance favored a preferred vendor.
D. The fixed weight scoring method did not fit the situation and variable weights should
have been used.
Give this one a try later!
B. The committee cannot change the evaluation criteria in the RFP
Having received a requisition from the using department to establish a term contract for
goods or services, the best way to begin putting that contract together is with
________________.
A. The end result in mind
B. A detailed specification or scope of work from the NIGP library
C. A similar contract from another agency
D. The boiler-plate of terms and conditions previously reviewed and approved by the
legal department.
Give this one a try later!
A. The end result in mind
The consideration of essential functions, delegations of authority, vital records
management and human capital is part of:
A. Contract administration planning
B. Continuity of operations planning
C. Major procurement planning
D. Staff reorganization planning
Give this one a try later!
, B. Continuity of operations planning
Why is the Request for Proposal (RFP) process often perceived as problematic by an
agency's leadership?
A. The award decision is very quantifiable.
B. The award decision is based on qualitative variables.
C. The price is rarely known on award.
D. The outcome of the RFP process is difficult to justify.
Give this one a try later!
B. The award decision is based on qualitative variables.
After assuming her new duties as a procurement manager, Janet discovers that the
policies and procedures need revising. For the best examples of policies, procedures,
forms, documents and other materials, she should obtain a copy of:
A. The Model Procurement Code
B. The Uniform Commercial Code
C. Her agency's code enforcement manual
D. Her state's statutes
Give this one a try later!
A. The Model Procurement Code
, An organization's mission statement should:
A. Express the organization's purpose for existence
B. Identify how the organization wants to function in the future
C. Articulate the goals and objectives of the organization
D. Communicate particular strategies for success
Give this one a try later!
A. Express the organization's purpose for existence
Which guideline describes how a procurement official should proceed when an award
protest is filed?
A. Always delay start of the project.
B. Always start the project since time is of the essence.
C. Decide whether or not to start the project after consulting legal counsel.
D. Seek a judicial decision
Give this one a try later!
C. Decide whether or not to start the project after consulting legal counsel
Constructive suspensions occur when a public agency is found to be responsible for a
work stoppage and yet they did not actually issue a suspension of work to the
contractor. There are seven examples noted in the literature
Give this one a try later!