When lifting personnel communication shall be maintained
between three of the next four
Person(s) being lifted - Operator - Signal person
The condition when the tower load block or hook assembly
comes in contact with the upper
Two-blocking
Load bearing members of the climbing and support system shall
be inspected before each
Climbing operation
Extensive planning must occur before a self erecting tower
crane arrives on the job site. The plan should be divided into
two major sections as follows
, Page 2 of 30
Delivery, set up, erection and dismantle - Lifting operations
Before each climbing operation all load members of the support
system shall be
Inspected
Chain slings are required to be
ID tagged
Welding on loads suspended by the crane can only be done if
the load has
Insulated slings
Splices in rall tracks shall have
Smooth Joints
Hydraulic systems should have their proper fluid level checked
, Page 3 of 30
Daily
If power fails during operations, the following shouldn't apply
Do your best to finish moving load where it was designated to
go
If load is undetermined who is to find out if load weight does
not exceed crane rating at radius at which the load is to be
lifted
Person responsible for lift
Where should climbing instructions be kept
ON Site
All climbing operations shall be performed under the
supervision of
Qualified person
NCCCO TOWER CRANE CERTIFICATION EXAM WITH
CORRECT ANSWERS GRADED A 2025
When lifting personnel communication shall be maintained
between three of the next four
Person(s) being lifted - Operator - Signal person
The condition when the tower load block or hook assembly
comes in contact with the upper
Two-blocking
Load bearing members of the climbing and support system shall
be inspected before each
Climbing operation
Extensive planning must occur before a self erecting tower
crane arrives on the job site. The plan should be divided into
two major sections as follows
, Page 2 of 30
Delivery, set up, erection and dismantle - Lifting operations
Before each climbing operation all load members of the support
system shall be
Inspected
Chain slings are required to be
ID tagged
Welding on loads suspended by the crane can only be done if
the load has
Insulated slings
Splices in rall tracks shall have
Smooth Joints
Hydraulic systems should have their proper fluid level checked
, Page 3 of 30
Daily
If power fails during operations, the following shouldn't apply
Do your best to finish moving load where it was designated to
go
If load is undetermined who is to find out if load weight does
not exceed crane rating at radius at which the load is to be
lifted
Person responsible for lift
Where should climbing instructions be kept
ON Site
All climbing operations shall be performed under the
supervision of
Qualified person