a critical way that formal communication differs from informal is that that formal
communication is binding upon the parties and informal communication in non binding
true
during communications with the contractor the COR may
provide clarification about concerns or issues
The COR may release information without consulting with the Contracting Officer or
Legal Counsel.
false
when dealing with noncompliance what is the most preferred solution
Have the contractor repair or replace the defective or non-conforming supplies, or
reperform the non conforming services at no additional cost
If a contractor is delinquent on a portion of a contract, and that portion is clearly
severable from the continuing portion of the contract, the Contracting Officer may
terminate the deficient portion of the contract using a Partial Termination.
True