ASPHALT PAVING CERT QUESTIONS AND CORRECT ANSWERS Below what ambient temperature is it no longer acceptable to place wearing course? CORRECT ANSW-50 degrees How many pavement samples shall be obtained for each mix use for a production sublot superpave asphaltic concrete? CORRECT ANSW-3 The amount of asphaltic concrete PLACED, calculated in lbs/yd^2, is called? CORRECT ANSW Actual yield Asphaltic concrete binder mixes shall not be applied when the ambient temperature is below ___________________? CORRECT ANSW-40 degrees

Mostrar más Leer menos
Institución
ASPHALT BINDERS
Grado
ASPHALT BINDERS









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ASPHALT BINDERS
Grado
ASPHALT BINDERS

Información del documento

Subido en
1 de marzo de 2025
Número de páginas
6
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

ASPHALT PAVING CERT QUESTIONS
AND CORRECT ANSWERS
Below what ambient temperature is it no longer acceptable to place wearing course? ✅✅
CORRECT ANSW-50 degrees



How many pavement samples shall be obtained for each mix use for a production sublot superpave
asphaltic concrete? ✅✅ CORRECT ANSW-3



The amount of asphaltic concrete PLACED, calculated in lbs/yd^2, is called? ✅✅ CORRECT ANSW-
Actual yield



Asphaltic concrete binder mixes shall not be applied when the ambient temperature is below
___________________? ✅✅ CORRECT ANSW-40 degrees



If a piece of certified paving equipment is not functioning properly, what action is the paving
inspector to take? ✅✅ CORRECT ANSW-Require correction or removal from project



When is a MTV required when placing asphaltic concrete on a roadway? ✅✅ CORRECT ANSW-
When placing the final 2 lifts on the roadway travel lanes



Which equipment used for paving must be certified in accordance with weight certification laws?
✅✅ CORRECT ANSW-haul truck

Who is responsible for selecting sample locations for pavement cores? ✅✅ CORRECT ANSW-The
departments certified inspector



Who is the certifying authority for equipment used on an asphaltic concrete paving project? ✅✅
CORRECT ANSW-The district-laboratory engineer



On what form is the daily inspection of all traffic control signs and devices to be documented?
✅✅ CORRECT ANSW-project diary



Where is the inspector required to document the location of each transverse joint? ✅✅ CORRECT
ANSW-field book

, Hot mix asphalt shall not be applied on a wet surface or when the ambient temperature is below
___________________________ for wearing course. ✅✅ CORRECT ANSW-50 degrees



What is the purpose of scrapers and watering devices on roller wheels? ✅✅ CORRECT ANSW-To
prevent mix from sticking to the wheels



How far from the centerline must the longitudinal joint in the top layer of pavement be if the
roadway is 2 lanes wide? ✅✅ CORRECT ANSW-3-6 inches



When mix is placed on a newly constructed cement or lime stabilized base, vibratory rollers shall not
be used for at least how many days? ✅✅ CORRECT ANSW-7 days



There shall be no more than ______________ ripples or peaks in every _______________ foot
section. ✅✅ CORRECT ANSW-12 and 100



The department will evaluate and verify the accuracy of an inertial profiler that is used for
determining the surface tolerance of asphaltic pavements in accordance with what DOTD test refer?
✅✅ CORRECT ANSW-TR 641 & TR 644



A taut piano wire which is stretched at a specified elevation (grade) along support stakes next to a
paving strip is known as a? ✅✅ CORRECT ANSW-erected string line



The temperature of the mix going through the paver shall not be cooler than: ✅✅ CORRECT
ANSW-250 degrees



The contractor shall test the pavement for rideability during the first day, but in no case later than
____________ days following laydown? ✅✅ CORRECT ANSW-7 days



Pavement samples shall be cores approximately _________ or _____________ in diameter taken by
an approved core drill. ✅✅ CORRECT ANSW-4 or 6 inches



To meet DOTD requirements, how large must the cover of a haul truck be? ✅✅ CORRECT ANSW-
Large enough to cover the top of the bed and extend over the sides

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
PEAKGRADES Chamberlain College Of Nursing
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
26
Miembro desde
1 año
Número de seguidores
6
Documentos
4006
Última venta
1 mes hace
PEAK GRADES

Hello everyone...Explore a wide range of Nursing Exams, Test Banks, Study Guides, and other valuable study materials on this page. If you need any additional resources, simply reach out to us, and we’ll deliver them promptly! Please remember to leave a review after your purchase to help us improve customer satisfaction. Thank you

4.3

4 reseñas

5
2
4
1
3
1
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes