________ is/are not required unless during monitoring you detected changes that
need to take place.
a. float time
b, controlling activities Ans✓✓✓ b. controlling activities
__________ project management methods address issues of extraordinary
uncertainty or complexity, and the project team must be able to collaboratively
problem solve in the field to guide the project toward success.
a. waterfall
b. extreme Ans✓✓✓ b. extreme
______________ process activities include documenting customer requirements,
estimating resource needs, finalizing the project budget, and creating the Work
Breakdown Structure.
a. closing
b. planning Ans✓✓✓ b. planning
A typical example of ____________ in a project is the involvement of many
different people, many different materials, and many different outcomes.
a. backlog
b. complexity
, c. uncertainty
d. scrum Ans✓✓✓ b. complexity
A typical example of complexity in a project is the involvement of many different
people, many different materials, and many different outcomes.
Agile project management is a(n) __________ approach to project management
where the project team works closely with the customer to deliver projects in
usable chunks.
a. structured
b. traditional
c. iterative Ans✓✓✓ c. iterative
Based on the fact that you can draw lessons learned from similar restaurant
projects done in the past, you expect that many of your project activity duration
times will vary. Because you are your own main stakeholder in this venture, there
will be very little movement in the project plan. Which project management
method is best for this project?
a. PERT
b. Agile
c. Extreme
d. CPM Ans✓✓✓ a. PERT