PMI PROJECT MANAGEMENT BASIC COURSE - PRACTIC
CAPM EXAM WITH VERIFIED SOLUTIONS
1.Which hof hthe hfollowing hare htailoring hconsiderations hfor hProject
hIntegration hManagement?: hProject hLife hCycle
2.Project hcost hcontrol hincludes hall hof hthe hfollowing hexcept: hAllocating hthe
hoverall hestimates hto hindividual hwork hpackages hto hestablish ha hcost
hbaseline
3.What his han houtput hof hPlan hScope hManagement?: hRequirements
hManagement hPlan
4.You hare hmanaging ha hproject hin hwhich hyou hintend hto hrespond hto hhigh
hlevels hof hchange hand hongoing hstakeholder hinvolvement. hThe hmost
hsuitable hproject hlife hcycle hfor hyour hproject his hthe:: hAdaptive hLife hCycle
5.Within hthe hConduct hProcurements hprocess, hexpert hjudgment hshould
hbe hconsidered hfrom hindividuals hor hgroup hwith hspecialized hknowledge hor
htraining hin hwhich hof hthe hfollowing htopics?: hProposal hEvaluation
6.Which hof hthe hfollowing hcan hbe hused has ha htool hand htechnique hin hthe
1 h/
h51
,hMonitor hand hControl hProject hWork hProcess?: hDecision hMaking
7.What hprocess hprioritizes hindividual hproject hrisks hfor hfuture hanalysis hor
haction hby hassessing htheir hprobability hof hoccurrence hand himpact?:
hPerform hQualitative hRisk hAnalysis
8.The hProject hCharter hestablishes ha hpartnership hbetween hwhich
horganiza- htions?: hPerforming hand hRequesting
9.Project hmanager hspend hthe hmajority hof htheir htime hcommunicating hwith
hteam hmembers hand hother hproject hstakeholders. hTo hcommunicate
heffectively, hthe hpro- hject hmanager hshould hgenerally hperform hall hof hthe
hfollowing hexcept:: hCalculating hthe hpotential hnumber hof hcommunication
hchannels haccurately
10.What his han houtput hof hthe hPerform hQualitative hRisks hAnalysis
hprocess?: hPro- hject hDocument hUpdates
11.Stakeholders hare:: hThe hpeople, hgroups, hor horganizations hthat
hcould himpact hor hbe himpacted hby ha hdecision, hactivity, hor houtcome
hof hthe hproject
12.All hof hthe hfollowing hare htrue habout haffinity hdiagrams hExcept:: hThey
hare hused hto hidentify hthe hkey hissues hto hbe hprioritized has ha hset hof
hdecisions hfor himplementation
13.Communication hactivities hhave hmany hpotential hdimensions hthat
hgenerally hinclude hall hof hthe hfollowing hEXCEPT:: hConceptual hand
hdefinitive
14.Personality hrefers hto hthe hindividual hdifferences hin hcharacteristic
hpatterns hof hthinking, hfeeling, hand hbehaving. hWhich hof hthe hfollowing hare
hthe hleast happro- hpriate hcharacteristics hfor hproject hmanagers?:
hComplexity, hcourteous, hintellectual, hcultural, hand hmanagerial
15.What htool hor htechnique his hused hto hobtain hinformation hfrom
hstakeholders hby hspeaking hwith hthem hdirectly?: hInterviews
16.Manage hStakeholder hEngagement hinvolves hall hof hthe hfollowing
hactivities hExcept:: hAvoiding hpotential hconcerns hthat hhave hnot hyet
hbecome hissues
2 h/
h51
,17.What hinput hto hthe hControl hCosts hprocess hcontain hdata hon hproject
hstatus hsuch has hwhich hcosts hhave hbeen hauthorized, hincurred, hinvoiced,
hand hpaid: hwork hperformance hdata
18.Which hcost-reimbursable hcontract hprovides hthe hseller hreimbursement
hfor hall hallowable hcosts hfor hperforming hthe hcontract hwork hand ha hfixed-fee
hpayment hcalculated has ha hpercentage hof hthe hinitial hestimated hproject
hcost?: hCost hplus hfixed hfee
19.Each hof hthe hfollowing his htrue habout hProject hStakeholder hManagement
hEx- hcept:: hFailure hto hmanage hand hcontrol hphysical hresources
hefficiently hmay hreduce hthe hchance hof hcompleting hthe hproject
hsuccessfully
20.Which hof hthe hfollowing hare htools hand htechniques hused hin hthe
hacquire hre- hsource hprocess?: hDecision hMaking
21.Precedence hDiagramming hMethod h(PDM) hshows:: hThe hlogical
hrelationships hthat hexist hbetween hactivities
22.Project hManagers hexhibit hdifferent hleadership hstyles. hEach hof hthe
hfollowing his ha hcommon hleadership hstyle hExcept:: hMotivational
23.Which hof hthe hfollowing hactivities hare hnecessary hfor hthe
hadministrative hclosure hof hthe hproject hor hphase?: hCollecting hany
hsuggestions hfor himproving hor hupdating hthe hpolicies hand hprocedures
hof hthe horganization hand hsending hthem hto hthe happropriate
horganizational hunit.
24.Completion hof hthe hproduct hscope his hmeasured hagainst hwhich hof hthe
hfollow- hing?: hProduct hRequirements
25.To hincrease hthe hchances hof hachieving hproject hsuccess, hthe hproject
hmanager hshould hdo hall hof hthe hfollowing hExcept:: hAs hmuch has hpossible,
hcreate hconflicts hamong hvarious hstakeholders hto hallow hthe hproject
hteam hto hget hoptimal hwork hdone.
26.Which hof hthe hfollowing his ha hPMIS htool hthat hcan hbe hused hto
hexecute hthe hManage hCommunications hprocess?: hSocial hMedia
hManagement
27.Which hof hthe hfollowing hare hexamples hof htacit hknowledge?: hCompetenc
28.The hproject hlife hcycle his hmanaged hby hexecuting ha hseries hof hproject
hmanage- hment hactivities. hThese hactivities hare hknown has:: hProject
hManagement hProcess
29.In hthe hPlan hRisk hResponses hprocess, han haccept hstrategy hfor ha
hnegative hrisk hor hthreat hindicates hthat hthe hproject hteam hhas hdecided:: hNot
hto hchange hthe hproject hmanagement hplan hto hdeal hwith ha hrisk, hor his
hunable hto hidentify hany hother hsuitable hresponse hstrategy
3 h/
h51
, 30.Culture his ha hpersonality hcharacteristic hor htrait hthat hincludes hwhich
hof hthe hfollowing hcomponents?: hValues, hnorm, hand hbeliefs
31.Which hof hthe hfollowing his hthe hprocess hof hestablishing hthe hpolicies,
hproce- hdures, hand hdocumentation hfor hplanning, hdeveloping, hmanaging,
hexecuting, hand hcontrolling hthe hproject hschedule?: hPlan hSchedule
hManagement
4 h/
h51
CAPM EXAM WITH VERIFIED SOLUTIONS
1.Which hof hthe hfollowing hare htailoring hconsiderations hfor hProject
hIntegration hManagement?: hProject hLife hCycle
2.Project hcost hcontrol hincludes hall hof hthe hfollowing hexcept: hAllocating hthe
hoverall hestimates hto hindividual hwork hpackages hto hestablish ha hcost
hbaseline
3.What his han houtput hof hPlan hScope hManagement?: hRequirements
hManagement hPlan
4.You hare hmanaging ha hproject hin hwhich hyou hintend hto hrespond hto hhigh
hlevels hof hchange hand hongoing hstakeholder hinvolvement. hThe hmost
hsuitable hproject hlife hcycle hfor hyour hproject his hthe:: hAdaptive hLife hCycle
5.Within hthe hConduct hProcurements hprocess, hexpert hjudgment hshould
hbe hconsidered hfrom hindividuals hor hgroup hwith hspecialized hknowledge hor
htraining hin hwhich hof hthe hfollowing htopics?: hProposal hEvaluation
6.Which hof hthe hfollowing hcan hbe hused has ha htool hand htechnique hin hthe
1 h/
h51
,hMonitor hand hControl hProject hWork hProcess?: hDecision hMaking
7.What hprocess hprioritizes hindividual hproject hrisks hfor hfuture hanalysis hor
haction hby hassessing htheir hprobability hof hoccurrence hand himpact?:
hPerform hQualitative hRisk hAnalysis
8.The hProject hCharter hestablishes ha hpartnership hbetween hwhich
horganiza- htions?: hPerforming hand hRequesting
9.Project hmanager hspend hthe hmajority hof htheir htime hcommunicating hwith
hteam hmembers hand hother hproject hstakeholders. hTo hcommunicate
heffectively, hthe hpro- hject hmanager hshould hgenerally hperform hall hof hthe
hfollowing hexcept:: hCalculating hthe hpotential hnumber hof hcommunication
hchannels haccurately
10.What his han houtput hof hthe hPerform hQualitative hRisks hAnalysis
hprocess?: hPro- hject hDocument hUpdates
11.Stakeholders hare:: hThe hpeople, hgroups, hor horganizations hthat
hcould himpact hor hbe himpacted hby ha hdecision, hactivity, hor houtcome
hof hthe hproject
12.All hof hthe hfollowing hare htrue habout haffinity hdiagrams hExcept:: hThey
hare hused hto hidentify hthe hkey hissues hto hbe hprioritized has ha hset hof
hdecisions hfor himplementation
13.Communication hactivities hhave hmany hpotential hdimensions hthat
hgenerally hinclude hall hof hthe hfollowing hEXCEPT:: hConceptual hand
hdefinitive
14.Personality hrefers hto hthe hindividual hdifferences hin hcharacteristic
hpatterns hof hthinking, hfeeling, hand hbehaving. hWhich hof hthe hfollowing hare
hthe hleast happro- hpriate hcharacteristics hfor hproject hmanagers?:
hComplexity, hcourteous, hintellectual, hcultural, hand hmanagerial
15.What htool hor htechnique his hused hto hobtain hinformation hfrom
hstakeholders hby hspeaking hwith hthem hdirectly?: hInterviews
16.Manage hStakeholder hEngagement hinvolves hall hof hthe hfollowing
hactivities hExcept:: hAvoiding hpotential hconcerns hthat hhave hnot hyet
hbecome hissues
2 h/
h51
,17.What hinput hto hthe hControl hCosts hprocess hcontain hdata hon hproject
hstatus hsuch has hwhich hcosts hhave hbeen hauthorized, hincurred, hinvoiced,
hand hpaid: hwork hperformance hdata
18.Which hcost-reimbursable hcontract hprovides hthe hseller hreimbursement
hfor hall hallowable hcosts hfor hperforming hthe hcontract hwork hand ha hfixed-fee
hpayment hcalculated has ha hpercentage hof hthe hinitial hestimated hproject
hcost?: hCost hplus hfixed hfee
19.Each hof hthe hfollowing his htrue habout hProject hStakeholder hManagement
hEx- hcept:: hFailure hto hmanage hand hcontrol hphysical hresources
hefficiently hmay hreduce hthe hchance hof hcompleting hthe hproject
hsuccessfully
20.Which hof hthe hfollowing hare htools hand htechniques hused hin hthe
hacquire hre- hsource hprocess?: hDecision hMaking
21.Precedence hDiagramming hMethod h(PDM) hshows:: hThe hlogical
hrelationships hthat hexist hbetween hactivities
22.Project hManagers hexhibit hdifferent hleadership hstyles. hEach hof hthe
hfollowing his ha hcommon hleadership hstyle hExcept:: hMotivational
23.Which hof hthe hfollowing hactivities hare hnecessary hfor hthe
hadministrative hclosure hof hthe hproject hor hphase?: hCollecting hany
hsuggestions hfor himproving hor hupdating hthe hpolicies hand hprocedures
hof hthe horganization hand hsending hthem hto hthe happropriate
horganizational hunit.
24.Completion hof hthe hproduct hscope his hmeasured hagainst hwhich hof hthe
hfollow- hing?: hProduct hRequirements
25.To hincrease hthe hchances hof hachieving hproject hsuccess, hthe hproject
hmanager hshould hdo hall hof hthe hfollowing hExcept:: hAs hmuch has hpossible,
hcreate hconflicts hamong hvarious hstakeholders hto hallow hthe hproject
hteam hto hget hoptimal hwork hdone.
26.Which hof hthe hfollowing his ha hPMIS htool hthat hcan hbe hused hto
hexecute hthe hManage hCommunications hprocess?: hSocial hMedia
hManagement
27.Which hof hthe hfollowing hare hexamples hof htacit hknowledge?: hCompetenc
28.The hproject hlife hcycle his hmanaged hby hexecuting ha hseries hof hproject
hmanage- hment hactivities. hThese hactivities hare hknown has:: hProject
hManagement hProcess
29.In hthe hPlan hRisk hResponses hprocess, han haccept hstrategy hfor ha
hnegative hrisk hor hthreat hindicates hthat hthe hproject hteam hhas hdecided:: hNot
hto hchange hthe hproject hmanagement hplan hto hdeal hwith ha hrisk, hor his
hunable hto hidentify hany hother hsuitable hresponse hstrategy
3 h/
h51
, 30.Culture his ha hpersonality hcharacteristic hor htrait hthat hincludes hwhich
hof hthe hfollowing hcomponents?: hValues, hnorm, hand hbeliefs
31.Which hof hthe hfollowing his hthe hprocess hof hestablishing hthe hpolicies,
hproce- hdures, hand hdocumentation hfor hplanning, hdeveloping, hmanaging,
hexecuting, hand hcontrolling hthe hproject hschedule?: hPlan hSchedule
hManagement