Follow-up work created after PM is considered... - correct answer ✔✔Corrective
When lubricating a bearing, the worst mistake would be to... - correct answer
✔✔Get dirt in the bearing
What would be classified as an unplanned downtime maintenance? - correct
answer ✔✔Reactive maintenance
Circuit testers determine if ___ electricity is present. - correct answer ✔✔AC
When checking for out of round, any movement of the dial indicates that the... -
correct answer ✔✔Shaft may be out of round
Preventive maintenance schedule would commonly include... - correct answer
✔✔Frequency
Scheduled replacement of minor parts that tend to wear quickly is an important
part of ___ maintenance. - correct answer ✔✔Preventive
In a PM audit, the ___ would likely be negatively impacted if there were large
uncompleted PM work orders. - correct answer ✔✔Mission statement