Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Examen

CCM Practice Exam || with Right Answers.

Puntuación
-
Vendido
-
Páginas
15
Grado
A+
Subido en
14-02-2025
Escrito en
2024/2025

The scope of work of the contract includes coordination with other entities, public utilities etc., entities over which neither you or the owner have any control, in order to complete the project. What strategies would be helpful to facilitate getting the necessary utility work done in a timely manner to avoid delays to the contractor? correct answers A. Contact utility companies early in the project life cycle; preferably during pre-design to determine all regulatory requirements, permitting, and provide all design documents and utility requirements B. Call the utility company a week before you need their work installed to keep your project moving. C. Invite representatives from the public utility companies to the pre-construction meeting D. Invite representatives from the public utility companies to attend regular progress meetings and practice ongoing partnering to accomplishing required tasks The start of a construction project is initiated with what type of letter? correct answers A. commissioning B. award C. notice to proceed (NTP) D. certification What is the term used for the project analysis process used to determine how best to meet the necessary function, performance, and reliability at the minimum life cycle cost? correct answers A. Building Information Modeling B. PERT estimation technique C. Value engineering D. Monte Carlo analysis Claims arising out of professional negligence are typically: correct answers A. covered under the owner's liability policy B. included in commercial general liability coverage C. excluded from commercial general liability coverage D. covered under the self-insured policy that all firms carry

Mostrar más Leer menos
Institución
CCM Practice
Grado
CCM Practice

Vista previa del contenido

CCM Practice Exam || with Right Answers.
The scope of work of the contract includes coordination with other entities, public utilities etc.,
entities over which neither you or the owner have any control, in order to complete the project.
What strategies would be helpful to facilitate getting the necessary utility work done in a timely
manner to avoid delays to the contractor? correct answers A. Contact utility companies early in
the project life cycle; preferably during pre-design to determine all regulatory requirements,
permitting, and provide all design documents and utility requirements

B. Call the utility company a week before you need their work installed to keep your project
moving.

C. Invite representatives from the public utility companies to the pre-construction meeting

D. Invite representatives from the public utility companies to attend regular progress meetings
and practice ongoing partnering to accomplishing required tasks

The start of a construction project is initiated with what type of letter? correct answers A.
commissioning

B. award

C. notice to proceed (NTP)

D. certification

What is the term used for the project analysis process used to determine how best to meet the
necessary function, performance, and reliability at the minimum life cycle cost? correct answers
A. Building Information Modeling

B. PERT estimation technique

C. Value engineering

D. Monte Carlo analysis

Claims arising out of professional negligence are typically: correct answers A. covered under the
owner's liability policy

B. included in commercial general liability coverage

C. excluded from commercial general liability coverage

D. covered under the self-insured policy that all firms carry

, Which of the following shows good construction management practice with respect to claim
mitigation? correct answers A. Reject any claim that does not meet the specific notice provisions
of the contract

B. Negotiate a settlement within 30 days of receiving each claim

C. Develop contemporaneous records and documentation

D. Delay responding to all claims until legal council has reviewed documentation

A major change in scope, requested by the owner, will cause the project's budget and the contract
completion date to be exceeded, even though the owner has emphatically told you that no
additional cost or time will be authorized. What should the CM do? correct answers A. Get the
Contracting Officer to issue the least cost option to the contract

B. Work with the designer and contractor to try to identify cost and time saving alternatives and
present the options to the owner

C. Tell the owner he's crazy and it can't be done

D. Issue a change order immediately

A dispute has arisen with the contractor and the owner wants to use a Dispute Review Board
(DRB) to resolve the issue. Which of the following issues will not allow the owner to use the
DRB approach to resolve the problem? correct answers A. The DRB provisions are not included
in the contract

B. Board members are neutral

C. All parties agree on the selection of the board members

D. Board members are acknowledged technical experts

What is the term used to define the detailed written description of the project requirements?
correct answers A. Drawings

B. Standards

C. Building Information Model

D. Specifications

On a public project, what is the first thing you should do when the contractor notifies you of an
unforseen condition encountered in the field during construction that will increase cost and time
of performance? correct answers A. Tell the contractor to submit an RFI and you'll look into it
when you have time

Escuela, estudio y materia

Institución
CCM Practice
Grado
CCM Practice

Información del documento

Subido en
14 de febrero de 2025
Número de páginas
15
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

$12.99
Accede al documento completo:

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
SirAnton NURSING, ECONOMICS, MATHEMATICS, BIOLOGY, AND HISTORY MATERIALS BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS, AND STUDY GUIDE MATERIALS WITH GUARANTEED A+ I am a dedicated medical practitioner with diverse knowledge in matters
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
758
Miembro desde
3 año
Número de seguidores
439
Documentos
38001
Última venta
5 horas hace
Reign Supreme Scholarly || Enlightened.

Get your revised study materials available here and elevate your educational outcomes. I have numerous verified learning materials (Research, Exams Questions and answers, Assignments, notes etc) for different courses guaranteed to boost your academic results. I am dedicated to offering you the best and unique learning content. You are encouraged to inquire further assistance from this end whenever need be. Kindly remember to leave your review, understanding your satisfaction is essential . We highly appreciate clients who always come back for more of the study content we offer, you are extremely valued. All the best.

Lee mas Leer menos
3.7

114 reseñas

5
49
4
20
3
22
2
8
1
15

Documentos populares

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes