©THESTAR 2024/2025 ALL RIGHTS RESERVED 11:42PM. A+ 1 Florida Electrical Business Exam #7 Questions With Correct Answers 100% Verified. The right to repossess or replevy unused materials from a jobsite will not be effective if someone, in good faith, purchased it after removal from the site of the improvement. - AnswerTrue. The contractor must within _____ days after the receipt of the property owner's request, furnishish to property owner or the property owner's agent a list of the subcontractors and suppliers who have a contract with the contractor as of the date the request is received by the contractor. - Answer10 days. A property perfected lien may be discharged by an order of the circuit court of the _____ where the property is located. - Answercounty When any interested party files a complaint, the clerk will issue a summons to the lienor to show cause within _____ days why his or her lien should not to be enforced by action or vacated and canceled of record. - Answer20 days If a lienor fails to show cause why his or her lien should not be enforced or fails to start such action before the return date of the summons, the court will immediately order cancellation of the lien. - AnswerTrue No lien provided by part 713.22 will continue for longer then ____ years after the claim of lien has been recorded. - Answer1 year No lien provided by part 713.22 will continue for no longer then _______ years after the recording of an amended claim of lien that shows a later date of final furnishing of labor, services, or materials. - Answer1 year The lien of any lienor upon whom Notice of contest of Lien is served and who fails to institute a suit to enforce his or her lien within ________ days after service of such notice will be extinguished automatically. - Answer60 ©THESTAR 2024/2025 ALL RIGHTS RESERVED 11:42PM. A+ 2 The payment bond is required to ______ an owner under s. 713.23 must be furnished by the contractor in at least the amount of the original contract price before commencing the construction of the improvement under the direct contract. - Answerexempt A copy the payment bond must be attached to the Notice of Commencement when it is _______. - Answerrecorded Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the ______ degree - Answerthird When a construction project is "put out" for bid, the contractors are given the plans and specifications for the project. If any deviations for these specifications occur, who will be held responsible and may be required to correct them at their own expense? - AnswerThe contractor The ______ for a protect are interpreted as a legal document that specifically defines the responsibilities of the owner and his representatives intended for the project and what the contractors responsibilities are. - Answerspecifications The CSI-MASTERFORMAT divides the specifications into __________ specific divisions to provide a standard reference and filing numbers for bidding and contract forms. - Answer50 Which of the following would appear as a heading in the index of the General Clauses and Conditions sections of General Requirements? - AnswerAll of these ( General Conditions, Notice to Bidders and Proposal) _________ is the contractors price for performing the work as specified. - AnswerThe proposal "Contract Documents" "Insurance," "payments," and "Guarantee" are some typical items that would be included under what heading in the General Clauses and Conditions section? - AnswerGeneral Conditions The square footage method of estimating is always recommended for lump-sum contracts. - AnswerFalse The typical _______ provides the necessary control devices for the accumulation of estimates into the final bid. - AnswerEstimate summary sheet What type of estimate is an accurate estimating method that consists of listing all material and labor needed for an element of work or project - AnswerDetailed Survey _________ estimates are used as a check to determine if sufficient materials are available to construct or complete a project. - AnswerMaterial Which of the following are types of la

Vista previa del contenido

©THESTAR 2024/2025 ALL RIGHTS RESERVED 11:42PM. A+




Florida Electrical Business Exam #7 Questions
With Correct Answers 100% Verified.


The right to repossess or replevy unused materials from a jobsite will not be effective if
someone, in good faith, purchased it after removal from the site of the improvement. -
Answer✔True.
The contractor must within _____ days after the receipt of the property owner's request,
furnishish to property owner or the property owner's agent a list of the subcontractors and
suppliers who have a contract with the contractor as of the date the request is received by the
contractor. - Answer✔10 days.
A property perfected lien may be discharged by an order of the circuit court of the _____ where
the property is located. - Answer✔county
When any interested party files a complaint, the clerk will issue a summons to the lienor to
show cause within _____ days why his or her lien should not to be enforced by action or
vacated and canceled of record. - Answer✔20 days
If a lienor fails to show cause why his or her lien should not be enforced or fails to start such
action before the return date of the summons, the court will immediately order cancellation of
the lien. - Answer✔True
No lien provided by part 713.22 will continue for longer then ____ years after the claim of lien
has been recorded. - Answer✔1 year
No lien provided by part 713.22 will continue for no longer then _______ years after the
recording of an amended claim of lien that shows a later date of final furnishing of labor,
services, or materials. - Answer✔1 year
The lien of any lienor upon whom Notice of contest of Lien is served and who fails to institute a
suit to enforce his or her lien within ________ days after service of such notice will be
extinguished automatically. - Answer✔60




1

, ©THESTAR 2024/2025 ALL RIGHTS RESERVED 11:42PM. A+


The payment bond is required to ______ an owner under s. 713.23 must be furnished by the
contractor in at least the amount of the original contract price before commencing the
construction of the improvement under the direct contract. - Answer✔exempt
A copy the payment bond must be attached to the Notice of Commencement when it is
_______. - Answer✔recorded
Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the ______
degree - Answer✔third
When a construction project is "put out" for bid, the contractors are given the plans and
specifications for the project. If any deviations for these specifications occur, who will be held
responsible and may be required to correct them at their own expense? - Answer✔The
contractor
The ______ for a protect are interpreted as a legal document that specifically defines the
responsibilities of the owner and his representatives intended for the project and what the
contractors responsibilities are. - Answer✔specifications
The CSI-MASTERFORMAT divides the specifications into __________ specific divisions to
provide a standard reference and filing numbers for bidding and contract forms. - Answer✔50
Which of the following would appear as a heading in the index of the General Clauses and
Conditions sections of General Requirements? - Answer✔All of these ( General Conditions,
Notice to Bidders and Proposal)

_________ is the contractors price for performing the work as specified. - Answer✔The
proposal
"Contract Documents" "Insurance," "payments," and "Guarantee" are some typical items that
would be included under what heading in the General Clauses and Conditions section? -
Answer✔General Conditions
The square footage method of estimating is always recommended for lump-sum contracts. -
Answer✔False
The typical _______ provides the necessary control devices for the accumulation of estimates
into the final bid. - Answer✔Estimate summary sheet
What type of estimate is an accurate estimating method that consists of listing all material and
labor needed for an element of work or project - Answer✔Detailed Survey
_________ estimates are used as a check to determine if sufficient materials are available to
construct or complete a project. - Answer✔Material
Which of the following are types of labor estimates?

2

Información del documento

Subido en
10 de febrero de 2025
Número de páginas
7
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$10.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TheStar
3.7
(140)
Vendido
712
Seguidores
178
Artículos
27005
Última venta
5 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes