A fill line in an oil burner system is a line used to: - ANSWER Fill the storage tank with
oil.
The aquastat is located - ANSWER Below the water line.
All heating, combustion, and cooking equipment shall be installed with adequate
clearances from _______ construction. - ANSWER Combustible
The equipment must be provided with ______ or the building construction shall be _____
_____. - ANSWER Insulation.
Fire Protected
During operation the surface of combustible construction materials will not be raised to
a temp higher than _____ degrees F. - ANSWER 170 degrees
Equipment shall be so that the means of access for ordinary operation and maintenance
will not be _______. - ANSWER Hazardous
Acceptance Tests:
Boilers shall not go into operation until they have been _____ and ____ and an equipment
____ _____ has been issued by the ______. - ANSWER Inspected and tested.
Use permit, commissioner
Periodic Inspections: All boilers shall be inspected at least _____ a _____. including
chimney connections. - ANSWER Once a year
, Owners Annual Statement: The owner of each boiler shall file an _____ written statement
with the ________, specifying the _____of each boiler and ______ for inspection. -
ANSWER Annual, commissioner, location, arrangement.
Field Tests: all piping and oil storage tanks shall be _______ tested for tightness by the
______ before the system is operated. - ANSWER Hydrostatically, contractor
The piping shall be tested at _____ times the max working pressure applicable to that
part of the piping system but at a pressure ____ than the test pressure required for the
storage tank. - ANSWER 1/2, less
The min pressure for testing tanks shall be ____ times the max working pressure but in
no case less than ____ psi. - ANSWER 1 1/2, 25 psi
The hydrostatic pressure shall be maintained until all ____ and _____ have been visually
inspected for ___, but in no case less than _____ hour. - ANSWER Joints, connections,
leaks, 1/2 hour.
A record shall be kept of the pressure test showing the name of the _____ and the _____
at which the piping and tank were tested. - ANSWER Contractor, pressure
Gas piping shall be tested by the _____ before operation. - ANSWER Contractor
For oil burning systems, ____ ____ giving instructions for the care and operation of the
system shall be permanently located in an easily _____ and _____ location near the
equipment. - ANSWER Instruction Cards, visible, accessible
No oil burning equipment shall be operated until an equipment ____ _____ has been
issued by the commissioner, the requirements of the ____ ____ control code have been
met and until the approval for the storage of ____ ____ has been given by the fire
commissioner. - ANSWER Use permit, air pollution, fuel oil
Every oil burning installation which is not fully automatic or requires preheating shall be
A fill line in an oil burner system is a line used to: - ANSWER Fill the storage tank with
oil.
The aquastat is located - ANSWER Below the water line.
All heating, combustion, and cooking equipment shall be installed with adequate
clearances from _______ construction. - ANSWER Combustible
The equipment must be provided with ______ or the building construction shall be _____
_____. - ANSWER Insulation.
Fire Protected
During operation the surface of combustible construction materials will not be raised to
a temp higher than _____ degrees F. - ANSWER 170 degrees
Equipment shall be so that the means of access for ordinary operation and maintenance
will not be _______. - ANSWER Hazardous
Acceptance Tests:
Boilers shall not go into operation until they have been _____ and ____ and an equipment
____ _____ has been issued by the ______. - ANSWER Inspected and tested.
Use permit, commissioner
Periodic Inspections: All boilers shall be inspected at least _____ a _____. including
chimney connections. - ANSWER Once a year
, Owners Annual Statement: The owner of each boiler shall file an _____ written statement
with the ________, specifying the _____of each boiler and ______ for inspection. -
ANSWER Annual, commissioner, location, arrangement.
Field Tests: all piping and oil storage tanks shall be _______ tested for tightness by the
______ before the system is operated. - ANSWER Hydrostatically, contractor
The piping shall be tested at _____ times the max working pressure applicable to that
part of the piping system but at a pressure ____ than the test pressure required for the
storage tank. - ANSWER 1/2, less
The min pressure for testing tanks shall be ____ times the max working pressure but in
no case less than ____ psi. - ANSWER 1 1/2, 25 psi
The hydrostatic pressure shall be maintained until all ____ and _____ have been visually
inspected for ___, but in no case less than _____ hour. - ANSWER Joints, connections,
leaks, 1/2 hour.
A record shall be kept of the pressure test showing the name of the _____ and the _____
at which the piping and tank were tested. - ANSWER Contractor, pressure
Gas piping shall be tested by the _____ before operation. - ANSWER Contractor
For oil burning systems, ____ ____ giving instructions for the care and operation of the
system shall be permanently located in an easily _____ and _____ location near the
equipment. - ANSWER Instruction Cards, visible, accessible
No oil burning equipment shall be operated until an equipment ____ _____ has been
issued by the commissioner, the requirements of the ____ ____ control code have been
met and until the approval for the storage of ____ ____ has been given by the fire
commissioner. - ANSWER Use permit, air pollution, fuel oil
Every oil burning installation which is not fully automatic or requires preheating shall be