All work performed on any component of a fire sprinkler system MUST be done by or
under the supervision of a - Answer-G. Card holder
Quarterly Inspections MUST be done by a - Answer-License holder or designee
Service Tags SHALL be hung on the - Answer-OS&Y valve after work is completed
The minimum number of heads in a box is - Answer-Six
The maximum working pressure of a fire sprinkler system is - Answer-175psi
A dry pipe valve and supply pipe SHALL be protected from - Answer-Freezing
How much notice must be given to the AHJ before a test or inspection can be
scheduled? - Answer-48 hours
When a fire sprinkler system has more than 20 sprinkler heads a - Answer-Fire
alarm is required
A fire sprinkler system MUST take no longer than _______ for water to reach the
most remote head - Answer-3 minutes
What is the minimum residual pressure required for a light hazard fire sprinkler
system? - Answer-15psi
The air pressure over the anticipated trip pressure of a dry fire sprinkler system
should not exceed - Answer-20psi
The maximum length of lateral sway bracing on a cross main is - Answer-40 feet
Pipe hangers SHALL be designed to hold the weight of the pipe filled with water plus
- Answer-250lbs at the point of the hanger
The all thread required to hang 5, 6 & 8 inch pipe is - Answer-1/2"
Fire sprinkler system piping SHALL be tested at 200psi for - Answer-2 hours
The water gauge SHALL be placed above and below the - Answer-Alarm check
valve
E.S.F.R (early suppression fast response) sprinkler heads are NOT allowed in -
Answer-Dry systems
Maintenance and inspection of fire sprinkler systems is found in - Answer-NFPA 25
T or F : NFPA 13 is for design, installation and water supply only - Answer-False