with 100% correct answers
2025
Which is a PRINCE2 principle?
A. Focus on the business need
B. Limit work in progress
C. Start with what you do now
D. Focus on products - answer D. Focus on products
Which is a purpose of the risk theme?
A. To establish mechanisms to control unacceptable deviations from
a plan
B. To identify, assess and control problems that have occurred
C. To improve the ability of the project to succeed by controlling
uncertainty D. To establish mechanisms to monitor the project's
continued viability - answer C. To improve the ability of the project
to succeed by controlling uncertainty
Which is a purpose of the 'managing a stage boundary' process?
A. To provide a fixed point to confirm acceptance of the project
product
B. To authorize the project manager to proceed to the next
management stage
C. To control the link between the project manager and the team
manager(s) D. To provide the project board with information to
, assess ongoing viability - answer D. To provide the project board
with information to assess ongoing viability
4) What is the project product description used for during the
'closing a project' process?
1. To validate that acceptance criteria have been achieved.
2. To check that the project has delivered what is expected.
3. To identify lessons learned throughout the project delivery.
4. To validate any benefits that have been realized so far.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4 - answer A. 1 and 2
1. To validate that acceptance criteria have been achieved.
2. To check that the project has delivered what is expected.
Which responsibilities are specifically assigned to the team
manager?
1. Ensuring that the required products are produced appropriately.
2. Delivering products within the time, cost and quality tolerances.
3. Representing the interests of those using the project's products.
4. Being accountable for the technical integrity of the whole project.
A. 1 and 2
B. 2 and 3