CON 367 MIDTERM EXAM WITH
COMPLETE SOLUTION
The process of initiating a construction project. - ANSWER 1. Advertise for
bids
2. Open bids
3. Award contract
4. Sign the contract
5. Issue notice to proceed
Under the Contractor Quality Control (CQC) process, inspection is provided
by the contractor - ANSWER False
Owners generally engage the services of a professional construction
management firm (Agency CM) in fast-track projects with multiple contracts.
- ANSWER True
A professional construction management firm (Agency CM) can participate in
the following phases of a project - ANSWER Conception, program planning,
Design, Construction and Closeout
The Design-Build (DB) project delivery process may face some barriers when
tried to be implemented in the public sector. - ANSWER True
In a project with multiple prime contractors, who is responsible for
coordinating the various trade contractors? - ANSWER Owner or its
representative (e.g. the construction manager)
, The Resident Project Representative should not direct the contractor's work.
- ANSWER True
Which of the following is under the authority of the Resident Project
Representative? - ANSWER To approve materials & worksmanship that meet
the contract requirements
Routing of submittals from the subcontractor to the Designer - ANSWER 1.
Subcontractor
2. Contractor
3. Resident Project Representative
4. Project Engineer
5. Design Reviews
The Resident Project Representative should obtain the contract documents
and study those as soon as being engaged to provide resident inspection on
a project. - ANSWER True
The Resident Project Representative does not need to make any
measurement for the progress payments in the lump-sum projects - ANSWER
False
When the Resident Project Representative identifies a problem with the
subcontractor's work, he/she should provide instructions directly to the
subcontractor. - ANSWER False
In a construction project, the general contractor should submit all submittals
(e.g., shop drawings, samples, etc...) directly to: - ANSWER
If the daily Construction Report is generated in the computer, it is advisable
COMPLETE SOLUTION
The process of initiating a construction project. - ANSWER 1. Advertise for
bids
2. Open bids
3. Award contract
4. Sign the contract
5. Issue notice to proceed
Under the Contractor Quality Control (CQC) process, inspection is provided
by the contractor - ANSWER False
Owners generally engage the services of a professional construction
management firm (Agency CM) in fast-track projects with multiple contracts.
- ANSWER True
A professional construction management firm (Agency CM) can participate in
the following phases of a project - ANSWER Conception, program planning,
Design, Construction and Closeout
The Design-Build (DB) project delivery process may face some barriers when
tried to be implemented in the public sector. - ANSWER True
In a project with multiple prime contractors, who is responsible for
coordinating the various trade contractors? - ANSWER Owner or its
representative (e.g. the construction manager)
, The Resident Project Representative should not direct the contractor's work.
- ANSWER True
Which of the following is under the authority of the Resident Project
Representative? - ANSWER To approve materials & worksmanship that meet
the contract requirements
Routing of submittals from the subcontractor to the Designer - ANSWER 1.
Subcontractor
2. Contractor
3. Resident Project Representative
4. Project Engineer
5. Design Reviews
The Resident Project Representative should obtain the contract documents
and study those as soon as being engaged to provide resident inspection on
a project. - ANSWER True
The Resident Project Representative does not need to make any
measurement for the progress payments in the lump-sum projects - ANSWER
False
When the Resident Project Representative identifies a problem with the
subcontractor's work, he/she should provide instructions directly to the
subcontractor. - ANSWER False
In a construction project, the general contractor should submit all submittals
(e.g., shop drawings, samples, etc...) directly to: - ANSWER
If the daily Construction Report is generated in the computer, it is advisable