A project manager's planning _____. - ANSWER includes identifying project tasks and
estimated completion times and costs
_____ is a full-featured program that holds the dominant share of the project
management software market. - ANSWER Microsoft Project
Effective project reporting requires ____. - ANSWER strong communication skills
In addition to tasks, every project has ____, which are reference points used to monitor
progress and manage the project. - ANSWER milestones
A risk management plan includes a review of ____. - ANSWER project scope
A(n) ____ chart can be used to display the qualitative risk analysis matrix. - ANSWER XY
____ is a possible cause of cost overruns related to human resource issues. - ANSWER
turnover
When several tasks can start at the same time, each is called a(n) ____ task. - ANSWER
concurrent
When an information system does not meet business requirements, causes might
include ____. - ANSWER imprecise targets
For a project manager, reporting _____. - ANSWER includes informing management,
users, and the project team
A ____ might involve maximums for one or more resources. - ANSWER constraint
Problems with timetables and project milestones can indicate ____. - ANSWER
personality conflicts
A event is a recognizable reference point that you can use to ____. - ANSWER monitor
progress
____ is open-source software that is supported by a community of users and developers.
- ANSWER GanttProject
The first step in the creation of a PERT/CPM chart is to ____. - ANSWER identify all
project tasks
The Apptivo ____ is free of charge with unlimited duration. - ANSWER standard plan
A project manager's scheduling function _____. - ANSWER involves staffing
, Microsoft claims that Microsoft Project has the capability of ____. - ANSWER assign
ownership of risks
Most risk identifications include a brief description of ____. - ANSWER who would be r
esponsible for responding to a given risk
Which of the following are metrics of a successful project ____. - ANSWER delivery of a
product that satisfies users
Microsoft's risk management model includes ____. - ANSWER category which specifies
risk type
A project triangle shows three legs: _____. - ANSWER cost, scope, time
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to
deal with it. - ANSWER response
A _____ cannot be started until one or more other tasks are completed. - ANSWER
dependent task
Many project managers find ____ charts more helpful for scheduling, monitoring, and
controlling projects. - ANSWER PERT/CPM
In an interview, ____ limit or restrict the response. - ANSWER closed-ended questions
RAD relies heavily on ____. - ANSWER prototyping
____ is a typical example of a system requirement for the output category. - ANSWER
The contact management system must generate a daily reminder list for all sales reps
____ is a typical example of a system requirement for the process category. - ANSWER
The equipment rental system must not execute new rental transactions for customers
who have overdue tapes
Supporters of neutral locations for interviews believe that it ____. - ANSWER keeps
interruptions to a minimum so people can concentrate fully
The primary advantage of RAD is that ____. - ANSWER systems can be developed more
quickly with significant cost savings
____ is a typical example of a system requirement for the input category. - ANSWER
Student grades must be entered on machine-scannable forms prepared by the
instructor
In an interview, ____ are questions that ask a person to evaluate something by providing
limited answers to specific responses or on a numeric scale. - ANSWER
range-of-response questions
A(n) ____ is a top-down representation of a function or a process. - ANSWER FDD
SOLUTION
A project manager's planning _____. - ANSWER includes identifying project tasks and
estimated completion times and costs
_____ is a full-featured program that holds the dominant share of the project
management software market. - ANSWER Microsoft Project
Effective project reporting requires ____. - ANSWER strong communication skills
In addition to tasks, every project has ____, which are reference points used to monitor
progress and manage the project. - ANSWER milestones
A risk management plan includes a review of ____. - ANSWER project scope
A(n) ____ chart can be used to display the qualitative risk analysis matrix. - ANSWER XY
____ is a possible cause of cost overruns related to human resource issues. - ANSWER
turnover
When several tasks can start at the same time, each is called a(n) ____ task. - ANSWER
concurrent
When an information system does not meet business requirements, causes might
include ____. - ANSWER imprecise targets
For a project manager, reporting _____. - ANSWER includes informing management,
users, and the project team
A ____ might involve maximums for one or more resources. - ANSWER constraint
Problems with timetables and project milestones can indicate ____. - ANSWER
personality conflicts
A event is a recognizable reference point that you can use to ____. - ANSWER monitor
progress
____ is open-source software that is supported by a community of users and developers.
- ANSWER GanttProject
The first step in the creation of a PERT/CPM chart is to ____. - ANSWER identify all
project tasks
The Apptivo ____ is free of charge with unlimited duration. - ANSWER standard plan
A project manager's scheduling function _____. - ANSWER involves staffing
, Microsoft claims that Microsoft Project has the capability of ____. - ANSWER assign
ownership of risks
Most risk identifications include a brief description of ____. - ANSWER who would be r
esponsible for responding to a given risk
Which of the following are metrics of a successful project ____. - ANSWER delivery of a
product that satisfies users
Microsoft's risk management model includes ____. - ANSWER category which specifies
risk type
A project triangle shows three legs: _____. - ANSWER cost, scope, time
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to
deal with it. - ANSWER response
A _____ cannot be started until one or more other tasks are completed. - ANSWER
dependent task
Many project managers find ____ charts more helpful for scheduling, monitoring, and
controlling projects. - ANSWER PERT/CPM
In an interview, ____ limit or restrict the response. - ANSWER closed-ended questions
RAD relies heavily on ____. - ANSWER prototyping
____ is a typical example of a system requirement for the output category. - ANSWER
The contact management system must generate a daily reminder list for all sales reps
____ is a typical example of a system requirement for the process category. - ANSWER
The equipment rental system must not execute new rental transactions for customers
who have overdue tapes
Supporters of neutral locations for interviews believe that it ____. - ANSWER keeps
interruptions to a minimum so people can concentrate fully
The primary advantage of RAD is that ____. - ANSWER systems can be developed more
quickly with significant cost savings
____ is a typical example of a system requirement for the input category. - ANSWER
Student grades must be entered on machine-scannable forms prepared by the
instructor
In an interview, ____ are questions that ask a person to evaluate something by providing
limited answers to specific responses or on a numeric scale. - ANSWER
range-of-response questions
A(n) ____ is a top-down representation of a function or a process. - ANSWER FDD