What was the cause of the major steam leak that occured on the USS Iwo Jima on
October 30th 1990? - ANSWERFailure of bonnet fasteners.
How often does the Quality Assurance officer evaluate the effectiveness of the ship's
Quality Assurance? - ANSWERQuarterly
Who is responsible for the preparation of a CWP on a ship? - ANSWERThe Quality
Insurance Inspector
Who is required to sign, print and date block 15B of the QA Form 9 for a shipboard
CWP? - ANSWERQuality Assurance Officer
Who is responsible for ensuring that the FWP provides the correct written
instructions, both in sequence and requirements, to satisfactorily accomplish the
controlled work? - ANSWERWork Center Supervisor
Which of the following individuals is not authorized to approve pen and ink changes
to QA forms in a CWP? - ANSWERQuality Assurance Advisor
What QA Form is used to document re-entry of the SUBSAFE system? -
ANSWERQA Form 9
Who is responsible for ensuring that divisional controlled material is probably
handled and stowed? - ANSWERControlled Material Petty Officer
Who prepares Controlled Work Packages at a FMA? - ANSWERPlanning and
Estimating Officer
Which of the following is not a function of a Quality Assurance Inspector? -
ANSWERSign CWP to grant approval for production work to commence.
What symbol would be used in an FWP to indicate the step requires inspection by a
NDT inspector? - ANSWER(I)
Which of the following is not a required element in a FWP? - ANSWERPrecautions
How is material for use in a Level I system designated when in the custody of the
end-user work center? - ANSWERLevel 1 SUBSAFE Stock Program Material
The CWP/FWP will be at the jobsite during the performance of the work. -
ANSWERTrue
What QA Form will be used to document satisfactory Hydrostatic/ Pneumatic tests? -
ANSWERQA Form 26