PMI Exam Prep
Which of the following refers to overseeing multiple projects? - answer-Project Management
In a project, which term indicates an important component that must be delivered by a specific date? -
answer-Milestone
Which two of the following statements are examples of defining the project scope in a project? -
answer--The website must contain six sections, one for each of the company's product types.
-The website must allow users to make online purchases from anywhere in the world.
Which of the following describes a project manager? - answer-Someone assigned within a company to
lead a project
In a project constructing block of apartments to sell as real estate, which two statements represent
risks? - answer--The general public may not buy houses if there is an economic crisis.
-There may be an earthquake during construction.
Which of the following is NOT part of the cost baseline? - answer-The management reserve
Which document gives the project manager the formal authority to manage a project? - answer-The
project charter
Which knowledge areas make up the dimensions of a project? - answer-Scope, Schedule, and Cost
Which two of the following sentences regarding programs and program managers are true? - answer--
The program manager can influence the project.
-A program is a group of related projects.
How should the project manager react if two team members have an argument about a technical
requirement in a project? - answer-Help the two to work together and find a joint solution
When a client refuses to communicate with the project manager due to a conflict, who is responsible for
resolving the problem? - answer-The sponsor and the project manager
Who should first try to resolve an internal conflict in project management? - answer-The project team
Which two of the following are key stakeholders? - answer-Client
Sponsor
Which term defines the job function assigned to a person within the scope of a project? - answer-Role
, What is the first thing a project manager should do at the start of a project? - answer-Identify the main
deliverables
Which of the following tools is used for defining, executing, and monitoring the deliverables of a
project? - answer-Work breakdown structure (WBS)
What are the different stages of a project timeline? - answer--Identify the activities
-Sequence the activities
-Estimate the duration
-Develop the timeline
What are three positive outcomes of a brainstorming session? - answer--Improving internal relationships
in the team
-Benefiting from the team's creativity
-Generating an extensive number of ideas
Which of the following is not a technique for data gathering? - answer-Cost baseline
Who in a project is given authority through the project charter? - answer-The project manager
What is the name of the meeting held at the end of the planning stage and at the beginning of the
execution stage? - answer-Kick off meeting
Which communication technique focuses on providing information about reactions to communications?
- answer-Feedback
Which three of the following actions does the Project Management Institute (PMI) recommend to
ensure an effective meeting? - answer--Check that the appropriate people are invited to the meeting
-Define and communicate the meeting agenda beforehand
-Ensure that the people invited attend
In which two situations is a traditional management approach recommended? - answer--When it is
possible to plan the project in the early stages of its lifecycle
-When there is certainty about the scope of the project
During the execution of a project, a key stakeholder asks for a change. Which actions should the project
manager carry out in order? - answer--Register the change request
-Qualify and quantify the impact of the change
-Look for alternatives to the change
-Take the change request to the appropriate business level for approval or rejection
Which statement properly characterizes the creation of a project management plan? - answer-It is done
gradually
In a traditional predictive project, which knowledge area should be the first to be defined? - answer-
Scope