CM 4100 Module 1-6 Exam Questions With Correct Answers A significant difference between "planning" and "scheduling" is, a.Scheduling determines what is going to be done, and planning determines how to do. a.Scheduling determines how to do, and planning determines what to do. a.Scheduling determines when to do, and planning determines what to do, how to do and by whom. Correct a.Scheduling determines how to do, and planning determines by whom. - answera. Scheduling determines what is going to be done, and planning determines how to do. What is not true about bar charts? a. Bar charts use a time-scaled presentation. b. Bar charts often directly show material consumption of each activity. c. Bar charts can show the relationships of each activity. d. Bar charts cannot show the actual status of a project. - answerb. Bar charts often directly show material consumption of each activity. What is not true about an activity? a. An activity usually takes time. b. An activity may consume resources. c. An activity usually has a start time and a finish time. d. An activity usually does not need to be measurable. - answerd. An activity usually does not need to be measurable. ©SIRJOEL EXAM SOLUTIONS 10/3/2024 9:54 PM What is not true about an event? a. An event usually takes time. b. An event usually consumes resources. c. An event is an activity. d. An event cannot have a start time or a finish time. e. All of the items listed - answere. All of the items listed What statements about a work breakdown structure (WBS) are true? a. A WBS describes the entire scope of the project. b. A WBS helps to organize project activities. c. The development of a WBS is a bottom up process, i.e.,from project details and up. d. A WBS usually needs to consider who is going to do a particular task. e. All of the items listed f. A and B - answerf. A and B What are the major types of activities? a. Production/construction b. Procurement c. Management d. All of the items listed - answerd. All of the items listed Reorder the list to show the logic sequence for developing a network model. A) Determine quantities and assign durations to activities B) Calculate early and late start/finish times C) Schedule activity start/finish times D) Define activities E) Compute float values and identify the critical path

Mostrar más Leer menos
Institución
CM 4100
Grado
CM 4100









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CM 4100
Grado
CM 4100

Información del documento

Subido en
16 de octubre de 2024
Número de páginas
7
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

©SIRJOEL EXAM SOLUTIONS
10/3/2024 9:54 PM


CM 4100 Module 1-6 Exam Questions With
Correct Answers

A significant difference between "planning" and "scheduling" is,


a.Scheduling determines what is going to be done, and planning determines how to do.
a.Scheduling determines how to do, and planning determines what to do.
a.Scheduling determines when to do, and planning determines what to do, how to do and by
whom.
Correct
a.Scheduling determines how to do, and planning determines by whom. - answer✔a. Scheduling
determines what is going to be done, and planning determines how to do.
What is not true about bar charts?


a. Bar charts use a time-scaled presentation.
b. Bar charts often directly show material consumption of each activity.
c. Bar charts can show the relationships of each activity.
d. Bar charts cannot show the actual status of a project. - answer✔b. Bar charts often directly
show material consumption of each activity.
What is not true about an activity?


a. An activity usually takes time.
b. An activity may consume resources.
c. An activity usually has a start time and a finish time.
d. An activity usually does not need to be measurable. - answer✔d. An activity usually does not
need to be measurable.

, ©SIRJOEL EXAM SOLUTIONS
10/3/2024 9:54 PM

What is not true about an event?


a. An event usually takes time.
b. An event usually consumes resources.
c. An event is an activity.
d. An event cannot have a start time or a finish time.
e. All of the items listed - answer✔e. All of the items listed
What statements about a work breakdown structure (WBS) are true?


a. A WBS describes the entire scope of the project.
b. A WBS helps to organize project activities.
c. The development of a WBS is a bottom up process, i.e.,from project details and up.
d. A WBS usually needs to consider who is going to do a particular task.
e. All of the items listed
f. A and B - answer✔f. A and B
What are the major types of activities?


a. Production/construction
b. Procurement
c. Management
d. All of the items listed - answer✔d. All of the items listed
Reorder the list to show the logic sequence for developing a network model.
A) Determine quantities and assign durations to activities
B) Calculate early and late start/finish times
C) Schedule activity start/finish times
D) Define activities
E) Compute float values and identify the critical path
$10.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
sirjoel Liberty University
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
108
Miembro desde
1 año
Número de seguidores
13
Documentos
11840
Última venta
3 días hace
Sirjoel

Here you will find all documents and package deals offered by sirjoel

3.5

17 reseñas

5
4
4
4
3
7
2
1
1
1

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes