Before leveling a mobile crane on outriggers, an operator should ensure: - answer-there is no weight of the crane bearing on any tires Operating a mobile crane with a long boom, on uneven ground, what support condition should be considered? - answer-Keeping 90 degree angle between cylinder rod and pad What is the primary purpose fir a rooster sheave or auxiliary boom point sheave? - answer-Separate the boom hoist lines How many randomly broken wires in a lay length must there be on a mobile cranes hoist line, before it should be removed from service? - answer-6 On a mobile crane, how many broken wires are permitted at the end connection of a pendent before it must be taken out of service? - answer-1 Type 1 rotation resistant hoist wire rope has a design factor of: - answer-5 to 1 How many randomly distributed broken wires in rotation- resistant hoist wire rope are considered for replacement? - answer-2 broken wires in 6 rope diameters The term net capacity is best defined by which of the terms listed below? - answer-Gross capacity minus capacity deductions Mobile cranes that are set up on barges, shall have a list chart provided by which of the entities listed below? - answer-Manufacturer When lifting loads on tires, mobile cranes are rated at what percentage of tipping? - answer-75% How does the effective weight of a slowed extension relate to the actual weight of the extension? - answer-Higher than the actual weight. When load radius is between radii values, the operator must use the: - answer-longer radius Why should only approved attachments or extra counterweights provided by the manufacturer be placed on the rear of the crane? - answer-They could cause a backward stability problem. A mobile crane's jib is offset 15º versus its original 0º offset, but the boom angle remains unchanged. In this situation, the load radius: - answer-increases Abruptly stopping a rapid swing on a long-boom mobile crane will produce what major effect? - answer-Collapsing the boom. When determining the position to a mobile crane should be left in over night, when high winds in the forecast the operator should: - answer-Follow the manufacturers recommendations. If a mobile crane is NOT set-up level and the operator swings the load from the high side to the low side, what effect will that have on the radius? - answer-The radius increase. Increasing the distance from the crane's center of gravity to the tipping axis will have what effect on the mobile crane? - answer-Decreases stability. Backward stability of a mobile crane is tested in which configuration listed below? - answer-Basic boom at minimum angle with no load Deflection of the boom while operating a mobile crane will increase? - answer-Load Radius (Swings out) A sudden start or stop of the hoisting function while operating a mobile crane can produce a: - answer-dynamic load Before lifting an occupied personnel platform on a job site, which of the following applies? - answer-Use 50% of rated capacity, Trial lift to anticipated weight, Ensure rigging dedicated to platform only. According to OSHA 1926. 1431, while hoisting a personnel platform, what weather condition listed below will promptly discontinue the operation? - answer-Dangerous If working near overhead power line and using a tag line, which type of rope is least conductive to electricity? - answer-Polypropylene When working near power lines with the mobile crane, where does OSHA require caution stickers be installed on all equipment? - answer-At operators station and 2 on the outside of the equipment. According to OSHA table T, what is the minimum clearance for 133kV power lines? - answer-10ft According to OSHA's table T, what clearance should a mobile crane IN TRANSIT keep while going under 445kV lines? - answer-16ft According to OSHA when is it safe to hoist loads with a mobile crane below energized power lines? - answer-When the fully extended boom can't reach the prohibited zone. According to OSHA 1926. 1411, when you encounter power lines with a voltage of 44kV and the crane is TRAVELING, according to Table T, what is the minimum required clearance? - answer-6ft According to OSHA, mobile crane load block hooks must not have a twist in excess of: - answer-0 According to OSHA, mobile crane load blocks hooks must not have a throat opening in excess of: - answer-5% When correctly installing U-bolt type wire rope clips, the U portion of the clip shall be on: - answer-the dead or short end What is the angle between the top of the load and the sling leg referred to in sling load charts? - answer-Horizontal sling angle When installing a wedge socket, it must be attached with the load line pulling in a straight line from the: - answer-pin What is the purpose of placing mats or cribbing under outrigger floats? - answer-Distribute the force over a larger area Where is the best location for leveling a crane? - answer-Upperworks When may blocking (cribbing) be placed under outrigger beams on mobile cranes? - answer-Never approved Mobile cranes should be level to within what percent of grade? - answer-1%

Vista previa del contenido

NCCCO CORE EXAM
Before leveling a mobile crane on outriggers, an operator should ensure: - answer-there is no weight of
the crane bearing on any tires

Operating a mobile crane with a long boom, on uneven ground, what support condition should be
considered? - answer-Keeping 90 degree angle between cylinder rod and pad

What is the primary purpose fir a rooster sheave or auxiliary boom point sheave? - answer-Separate the
boom hoist lines

How many randomly broken wires in a lay length must there be on a mobile cranes hoist line, before it
should be removed from service? - answer-6

On a mobile crane, how many broken wires are permitted at the end connection of a pendent before it
must be taken out of service? - answer-1

Type 1 rotation resistant hoist wire rope has a design factor of: - answer-5 to 1

How many randomly distributed broken wires in rotation- resistant hoist wire rope are considered for
replacement? - answer-2 broken wires in 6 rope diameters

The term net capacity is best defined by which of the terms listed below? - answer-Gross capacity minus
capacity deductions

Mobile cranes that are set up on barges, shall have a list chart provided by which of the entities listed
below? - answer-Manufacturer

When lifting loads on tires, mobile cranes are rated at what percentage of tipping? - answer-75%

How does the effective weight of a slowed extension relate to the actual weight of the extension? -
answer-Higher than the actual weight.

When load radius is between radii values, the operator must use the: - answer-longer radius

Why should only approved attachments or extra counterweights provided by the manufacturer be
placed on the rear of the crane? - answer-They could cause a backward stability problem.

A mobile crane's jib is offset 15º versus its original 0º offset, but the boom angle remains unchanged. In
this situation, the load radius: - answer-increases

Abruptly stopping a rapid swing on a long-boom mobile crane will produce what major effect? - answer-
Collapsing the boom.

When determining the position to a mobile crane should be left in over night, when high winds in the
forecast the operator should: - answer-Follow the manufacturers recommendations.

, If a mobile crane is NOT set-up level and the operator swings the load from the high side to the low side,
what effect will that have on the radius? - answer-The radius increase.

Increasing the distance from the crane's center of gravity to the tipping axis will have what effect on the
mobile crane? - answer-Decreases stability.

Backward stability of a mobile crane is tested in which configuration listed below? - answer-Basic boom
at minimum angle with no load

Deflection of the boom while operating a mobile crane will increase? - answer-Load Radius (Swings out)

A sudden start or stop of the hoisting function while operating a mobile crane can produce a: - answer-
dynamic load

Before lifting an occupied personnel platform on a job site, which of the following applies? - answer-Use
50% of rated capacity, Trial lift to anticipated weight, Ensure rigging dedicated to platform only.

According to OSHA 1926. 1431, while hoisting a personnel platform, what weather condition listed
below will promptly discontinue the operation? - answer-Dangerous

If working near overhead power line and using a tag line, which type of rope is least conductive to
electricity? - answer-Polypropylene

When working near power lines with the mobile crane, where does OSHA require caution stickers be
installed on all equipment? - answer-At operators station and 2 on the outside of the equipment.

According to OSHA table T, what is the minimum clearance for 133kV power lines? - answer-10ft

According to OSHA's table T, what clearance should a mobile crane IN TRANSIT keep while going under
445kV lines? - answer-16ft

According to OSHA when is it safe to hoist loads with a mobile crane below energized power lines? -
answer-When the fully extended boom can't reach the prohibited zone.

According to OSHA 1926. 1411, when you encounter power lines with a voltage of 44kV and the crane is
TRAVELING, according to Table T, what is the minimum required clearance? - answer-6ft

According to OSHA, mobile crane load block hooks must not have a twist in excess of: - answer-0

According to OSHA, mobile crane load blocks hooks must not have a throat opening in excess of: -
answer-5%

When correctly installing U-bolt type wire rope clips, the U portion of the clip shall be on: - answer-the
dead or short end

What is the angle between the top of the load and the sling leg referred to in sling load charts? - answer-
Horizontal sling angle

Información del documento

Subido en
15 de octubre de 2024
Número de páginas
8
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$10.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TOPDOCTOR
5.0
(1)
Vendido
10
Seguidores
5
Artículos
3387
Última venta
1 año hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes