BIM Unit 5 Exam Questions Correctly Answered. A _____ is an endeavor to accomplish a specific objective through a unique set of interrelated tasks and the effective utilization of resources. Select one: A. work schedule B. projection C. project D. task list - CORRECT ANSWER Project The _____ of a project is usually defined in terms of scope, schedule, and cost. Select one: A. performance B. schedule C. adjective D. objective - CORRECT ANSWER objective The successful accomplishment of the project objective is usually constrained by four factors: Select one: A. resource, cost, schedule, and customer satisfaction B. scope, quality, schedule, and customer satisfaction C. scope, cost, schedule, and customer satisfaction D. scope, cost, schedule, and completion - CORRECT ANSWER scope, cost, schedule, and customer satisfaction All of the work that must be done in order to satisfy the customer that the deliverables meet the requirement or acceptance criteria agreed upon at the onset of the project is called: Select one:

Vista previa del contenido

BIM Unit 5 Exam Questions Correctly
Answered.
A _____ is an endeavor to accomplish a specific objective through a unique set of interrelated tasks and
the effective utilization of resources.

Select one:

A. work schedule

B. projection

C. project

D. task list - CORRECT ANSWER Project



The _____ of a project is usually defined in terms of scope, schedule, and cost.

Select one:

A. performance

B. schedule

C. adjective

D. objective - CORRECT ANSWER objective



The successful accomplishment of the project objective is usually constrained by four factors:

Select one:

A. resource, cost, schedule, and customer satisfaction

B. scope, quality, schedule, and customer satisfaction

C. scope, cost, schedule, and customer satisfaction

D. scope, cost, schedule, and completion - CORRECT ANSWER scope, cost, schedule, and customer
satisfaction



All of the work that must be done in order to satisfy the customer that the deliverables meet the
requirement or acceptance criteria agreed upon at the onset of the project is called:

Select one:

, A. scope

B. plan

C. schedule

D. objective - CORRECT ANSWER scope



The project _____ usually states the time by which the project scope must be completed in terms of a
specific date agreed upon by the customer and the organization performing the work.

Select one:

A. objective

B. schedule

C. plan

D. request for proposal - CORRECT ANSWER objective



Ultimately, the responsibility of the project manager is to:

Select one:

A. finish the project as quickly as possible

B. finish the project as cost effectively as possible

C. make sure the customer is satisfied

D. make independent decisions - CORRECT ANSWER make sure the customer is satisfied



What are the four phases of the project life cycle?

Select one:

A. Identify a need, plan, develop a proposed solution, perform the project.

B. Plan, identify a need, develop a proposed solution, perform the project.

C. Identify a need, develop a proposed solution, terminate the project, repeat.

D. Identify a need, develop a proposed solution, perform the project, terminate the project. - CORRECT
ANSWER Identify a need, develop a proposed solution, perform the project, terminate the project.



This first phase of the project life cycle involves the:

Información del documento

Subido en
11 de octubre de 2024
Número de páginas
6
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$11.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Nursewendo
3.7
(22)
Vendido
71
Seguidores
19
Artículos
4976
Última venta
2 meses hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes