1. In which project management process group is the detailed project budget created? A. Initiating B. Before the project management process C. Planning D. Executing - ANSWER Answer C Notice the use of the word 'detailed'. Such a budget is created during the planning process group. 2. The project charter is created in which project management process group? A. Executing

Mostrar más Leer menos
Institución
PMP
Grado
PMP









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PMP
Grado
PMP

Información del documento

Subido en
7 de octubre de 2024
Número de páginas
9
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

  • pmp

Vista previa del contenido

PMP Rita Exam Prep Questions - Chapter 3
Project Mgmt Processes CORRECT 100%
1. In which project management process group

is the detailed project budget created?



A. Initiating

B. Before the project management process

C. Planning

D. Executing - ANSWER Answer C

Notice the use of the word 'detailed'. Such a budget

is created during the planning process group.



2. The project charter is created in which project management process group?



A. Executing

B. Planning

C. Closing

D. Initiating - ANSWER Answer D

The project charter is needed before planning and execution of the work can begin.



3. The project team has just completed the initial project schedule and budget. The NEXT thing to do is:



A. Identify risks

B. Begin iterations

C. Determine communications requirements

D. Create a bar (Gantt) chart - ANSWER Answer C

, Communications requirements and quality standards are needed before risks (especially risks relating to
communications and quality) can be determined (choice A). Iterations (choice B) cannot begin until the
risks are identified, qualified, quantified, and responses developed.

These then create the need to revise the WBS and other parts of the project management plan.

A bar chart (choice D) would have been done during the creation of the schedule, so it cannot be the
next thing. Of the choices listed, determine communications requirements (choice C) is the best.



4. A detailed project schedule can be created only after creating the:



A. Project budget

B. Work breakdown structure

C. Project management plan

D. Detailed risk assessment - ANSWER Answer B

In the project management process, the project budget (choice A), project management plan (choice C),
and detailed risk assessment (choice D) come after the schedule. The only answer that could be an input
is the WBS.



5. The person who should be in control of the project during project planning is the:



A. Project manager

B. Team member

C. Functional manager

D. Sponsor - ANSWER Answer A

The project manager should be named early in the project, during project initiating if possible.



6. Which of the following is NOT an input to the initiating process group?



A. Company processes

B. Company culture

C. Historical WBSs

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lecchris West Virgina University
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
40
Miembro desde
2 año
Número de seguidores
15
Documentos
3203
Última venta
1 mes hace
LECCHRIS

3.8

6 reseñas

5
2
4
1
3
3
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes