Examen

PMP 2024 Certification Exam Prep CORRECT 100%

Document preview thumbnail
Vista previa 4 fuera de 95 páginas

Plan Schedule Management (Process 2) Project Schedule Management (KA) - ANSWER What are the Outputs of the 'Define Scope'? - ANSWER Process 4, Planning, Project Scope Management (KA) How many processes in Project Integration Management knowledge area? - ANSWER Seven What are the seven processes of the Project Integration Management knowledge area? - ANSWER 1. Develop Project Charter 2. Develop Project Management Plan 3. Direct and Manage Project Work 4. Manage Project Knowledge

Vista previa del contenido

PMP 2024 Certification Exam Prep CORRECT 100%

Plan Schedule Management (Process 2)

Project Schedule Management (KA) - ANSWER



What are the Outputs of the 'Define Scope'? - ANSWER Process 4, Planning, Project Scope Management
(KA)



How many processes in Project Integration Management knowledge area? - ANSWER Seven



What are the seven processes of the Project Integration Management knowledge area? - ANSWER 1.
Develop Project Charter

2. Develop Project Management Plan

3. Direct and Manage Project Work

4. Manage Project Knowledge

5. Monitor and Control Project Work

6. Perform Integrated Change Control

7. Close Project or Phase.



Develop Project Charter - ANSWER The process of developing a document that formally authorizes the
existence of a project and provides the project manager with the authority to apply organizational
resources to project activities.



Develop Project Charter

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 1,
Initiating



Develop Project Management Plan - ANSWER The process of defining, preparing, and coordinating all
subsidiary plans and integrating them into a comprehensive project management plan.

, Develop Project Management Plan

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 2, Planning



Direct and Manage Project Work - ANSWER The process of leading and performing the work defined in
the project management plan and implementing approved changes to achieve the project's objectives.



Direct and Manage Project Work

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 3,
Executing



Manage Project Knowledge - ANSWER The process of using existing knowledge and creating new
knowledge to achieve the project's objectives and contribute to organizational learning.



Manage Project Knowledge

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 4,
Executing



Monitor and Control Project Work - ANSWER The process of tracking, reviewing, and reporting the
progress to meet the performance objectives defined in the project management plan.



Monitor and Control Project Work

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 5, M&C



Perform Integrated Change Control - ANSWER The process of reviewing all change requests; approving
changes and managing changes to deliverables, organizational process assets, project documents, and
the project management plan; and communicating their disposition.



Perform Integrated Change Control

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 6, M&C



Close Project or Phase - ANSWER The process of finalizing all activities for the project, phase, or contract.

, Close Project or Phase

Knowledge Area, Process #, Focus Group - ANSWER Project Integration Management, Process 7, Closing

What are the outputs of 'Develop Project Charter'? - ANSWER 1. Project Charter

2. Assumption Log



What document formally initiates the project? - ANSWER An approved project charter



When is the best time to assign a project manager? - ANSWER A project manager is identified and
assigned as early in the project as feasible, preferably while the project charter is being developed and
ALWAYS prior to the start of the planning.



Who develops the project charter? - ANSWER The project charter can be developed by the sponsor or
the project manager in collaboration with the initiating entity.



What authority does the project charter provide the project manager? - ANSWER With the project
charter, the project manager is provided the authority to plan, execute, and control the project.



(True or False) A project charter is a contract. - ANSWER False. A project charter is not considered to be a
contract because there is no consideration or money promised or exchanged in its creation.



What is the document most commonly used to create the project charter? - ANSWER The approved
business case. This business document most commonly used to create the project charter.



Business case - ANSWER The business case describes the necessary information from a business
standpoint to determine whether the expected outcomes of the project justify the required investment.
This is a cost-benefit analysis for go on a project.



The Project Charter incorporates information from... - ANSWER The business documents



Enterprise Environment Factors (EEFs) - ANSWER The factors that can influence the Develop Project
Charter process is:

, -Government or Industry standards

-Legal and regulatory requirements and/or constraints

-Marketplace conditions

-Organizational culture and political climate

-Organizational governance framework

-Stakeholders' expectations and risk thresholds



Organizational Process Assets (OPAs) - ANSWER The factors that can influence the Develop Project
Charter process is:

-Organizational standard policies, processes, and procedures

-Portfolio, program, and project governance framework (governance functions and processes to provide
guidance and decision making)

-Monitoring and reporting methods

-Templates (project charter template)

-Historical information and lessons learned repository



Expert Judgment; Tool and Technique Project Integration Management - ANSWER Judgment provided
based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for
the activity being performed. Such expertise may be provided by any group or person with specialized
education, knowledge, skill, experience, or training.



Data Gathering; Tool and Technique Project Integration Management - ANSWER -Brainstorming

-Focus Groups

-Interviews



Data Gathering: Brainstorming

Tool and Technique Project Integration Management - ANSWER This technique is used to identify a list of
ideas in a short period of time. Idea generation and analysis.



Data Gathering: Focus Groups

Información del documento

Subido en
7 de octubre de 2024
Número de páginas
95
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$15.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lecchris
3.8
(6)
Vendido
43
Seguidores
15
Artículos
3198
Última venta
3 meses hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes