• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 3 fuera de 21 páginas
Examen

Ccm Practice Exam With Answers

Document preview thumbnail
Vista previa 3 fuera de 21 páginas

CCM PRACTICE EXAM WITH ANSWERS The scope of work of the contract includes coordination with other entities, public utilities etc., entities over which neither you or the owner have any control, in order to complete the project. What strategies would be helpful to facilitate getting the necessary utility work done in a timely manner to avoid delays to the contractor? ANSWER A. Contact utility companies early in the project life cycle; preferably during pre-design to determine all regulatory requirements, permitting, and provide all design documents and utility requirements B. Call the utility company a week before you need their work installed to keep your project moving. C. Invite representatives from the public utility companies to the pre-construction meeting D. Invite representatives from the public utility companies to attend regular progress meetings and practice ongoing partnering to accomplishing required tasks The start of a construction project is initiated with what type of letter? ANSWER A. commissioning B. award C. notice to proceed (NTP) D. certification

Vista previa del contenido

CCM PRACTICE EXAM WITH
ANSWERS




The scope of work of the contract includes coordination with
other entities, public utilities etc., entities over which neither you
or the owner have any control, in order to complete the project.
What strategies would be helpful to facilitate getting the
necessary utility work done in a timely manner to avoid delays
to the contractor? ANSWER A. Contact utility companies early
in the project life cycle; preferably during pre-design to
determine all regulatory requirements, permitting, and provide
all design documents and utility requirements

B. Call the utility company a week before you need their work
installed to keep your project moving.

C. Invite representatives from the public utility companies to the
pre-construction meeting

D. Invite representatives from the public utility companies to
attend regular progress meetings and practice ongoing
partnering to accomplishing required tasks

The start of a construction project is initiated with what type of
letter? ANSWER A. commissioning

B. award

C. notice to proceed (NTP)

D. certification

,What is the term used for the project analysis process used to
determine how best to meet the necessary function,
performance, and reliability at the minimum life cycle cost?
ANSWER A. Building Information Modeling

B. PERT estimation technique

C. Value engineering

D. Monte Carlo analysis

Claims arising out of professional negligence are typically:
ANSWER A. covered under the owner's liability policy

B. included in commercial general liability coverage

C. excluded from commercial general liability coverage

D. covered under the self-insured policy that all firms carry

Which of the following shows good construction management
practice with respect to claim mitigation? ANSWER A. Reject
any claim that does not meet the specific notice provisions of
the contract

B. Negotiate a settlement within 30 days of receiving each
claim

C. Develop contemporaneous records and documentation

D. Delay responding to all claims until legal council has
reviewed documentation

A major change in scope, requested by the owner, will cause
the project's budget and the contract completion date to be
exceeded, even though the owner has emphatically told you

, that no additional cost or time will be authorized. What should
the CM do? ANSWER A. Get the Contracting Officer to issue
the least cost option to the contract

B. Work with the designer and contractor to try to identify cost
and time saving alternatives and present the options to the
owner

C. Tell the owner he's crazy and it can't be done

D. Issue a change order immediately

A dispute has arisen with the contractor and the owner wants to
use a Dispute Review Board (DRB) to resolve the issue. Which
of the following issues will not allow the owner to use the DRB
approach to resolve the problem? ANSWER A. The DRB
provisions are not included in the contract

B. Board members are neutral

C. All parties agree on the selection of the board members

D. Board members are acknowledged technical experts

What is the term used to define the detailed written description
of the project requirements? ANSWER A. Drawings

B. Standards

C. Building Information Model

D. Specifications

On a public project, what is the first thing you should do when
the contractor notifies you of an unforseen condition
encountered in the field during construction that will increase

Información del documento

Subido en
28 de agosto de 2024
Número de páginas
21
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$13.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
2
Seguidores
0
Artículos
401
Última venta
6 meses hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes