PJM GENERATION OPERATION Evatee 6/29/24 PJM GENERATION OPERATION PJM GENERATION OPERATION EXAM 2024 QUESTIONS WITH COMPLETE SOLUTIONS!!
Control center facilities must have a minimum of how many days of fuel for the
backup generator? Answer - 5 days
Control center facilities must have a minimum of how many days of fuel for the
backup generator? Answer - 5 days
If PJM ACE shows overgeneration, actual imports are: Answer - Less than scheduled
If PJM ACE shows overgeneration, actual imports are: Answer - Less than scheduled
Who should a generator contact at PJM to clear an outage ticket? Answer - Master Coordinator
Who should a generator contact at PJM to clear an outage ticket? Answer - Master Coordinator
To correct for a slow or fast clock, system frequency schedules are offset by: Answer - +/-.02 Hz To correct for a slow or fast clock, system frequency schedules are offset by: Answer - +/-.02 Hz
What frequency would PJM set to correct for fast-time error? Answer - 59.98Hz
What frequency would PJM set to correct for fast-time error? Answer - 59.98Hz
What frequency would PJM set to correct for slow-time error? Answer - 60.02Hz
What frequency would PJM set to correct for slow-time error? Answer - 60.02Hz
What info is on an instantaneous reserve check? Answer - synchronized (regulating and non-regulating), quick start, secondary and beyond secondary reserves
What info is on an instantaneous reserve check? Answer - synchronized (regulating and non-regulating), quick start, secondary and beyond secondary reserves
Generators must provide PJM with a realistic Reactive Capability Curve. This curve must have no less than __ points, and no more than __ points. Answer - No less than 2 and no more than 8 points
Generators must provide PJM with a realistic Reactive Capability Curve. This curve must have no less than __ points, and no more than __ points. Answer - No less than 2 and no more than 8 points