ACI Concrete Field Testing Technician- Grade I
The sensor of the temperature measuring device shall be submerged a minimum of _____ in.
[_____mm] into the freshly mixed concrete. - ANS-3 in. [75 mm]
The temperature measuring device shall have a capacity of measuring temperature of freshly
mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____. - ANS-1
degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]
The temperature measuring device shall be calibrated _____, or whenever there is a question of
_____. - ANS-Annually, accuracy
The temperature of concrete may be measured in a wheelbarrow. True or False? - ANS-True
The temperature of concrete may be measured in a wall form. True of False - ANS-True
A composite sample of concrete is required even if the only purpose for obtaining the sample is
to determine temperature. True of False? - ANS-False
What must be done to the sample container prior to sampling the concrete? - ANS-Dampen
(with water)
What must be done to the concrete surrounding the temperature measuring device after the
device is submerged in the fresh concrete. - ANS-Gently press the concrete around the
temperature measuring device at the surface of the concrete
How long must the temperature measuring device remain in the freshly mixed concrete? -
ANS-At least 2 minutes but not more than 5 minutes
After the temperature of the concrete is read, what is required? - ANS-Reporting of temperature
The temperature of concrete is reported to the nearest _____ degrees F [_____ C] - ANS-1
degree F [0.5 C]
According to ASTM C1064, what is one reason to take the temperature of concrete? -
ANS-Verify conformance to a specified requirement for temperature of concrete
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True of False? -
ANS-False
The sample of concrete used for temperature determination must be rodded 25 times. True or
False? - ANS-False
, Sampling by this method is required when tests are to be made to determine _____ with
specification requirements. - ANS-Compliance
This method covers sampling from four types of mixtures which are _____, _____, _____, and
_____. - ANS-Stationary mixers, paving mixers, revolving drum mixers, and open top mixers
The maximum allowable time between obtaining the first and final portions of a composite
sample is _____ minutes. - ANS-15
Portions of a composite sample shall be thoroughly remixed bfore beginning tests on the
sample. True of False? - ANS-True
The maximum elapsed time allowed between obtaining the final portion of the composite
sample and beginning the tests for slump, temperature, and air content is _____ minutes. -
ANS-5
The molding of strength test specimens shall begin within _____ minutes after fabricating the
composite sample. - ANS-15
The concrete sample must be protected from contamination and _____. - ANS-Rapid
evaporation
The minimum size sample for making strength test specimens is _____. - ANS-28 L (1ft^3)
When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly
spaced intervals during discharge of the middle portion of the batch - ANS-2
The composite sample for a paving mixer must represent a minimum of _____ different portions
of the batch of concrete taken from the pile after discharge. - ANS-5
When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of
_____ regularly spaced intervals during discharge of the middle portion of this batch. - ANS-2
Concrete samples from a truck mixer must be obtained before any water or admixtures are
added to the mixer at the job site. True or False? - ANS-False
The composite samples from a truck mixer must be obtained from the _____ portion of the
batch. - ANS-Middle
When the concrete contains aggregate larger than that permitted for a particular test method,
the sample of concrete must be _____ _____ before making the test. - ANS-Wet sieved
The slump test is applicable to plastic concrete with a maximum size aggregate of _____. -
ANS-1.5 in. [37.5 mm]
The sensor of the temperature measuring device shall be submerged a minimum of _____ in.
[_____mm] into the freshly mixed concrete. - ANS-3 in. [75 mm]
The temperature measuring device shall have a capacity of measuring temperature of freshly
mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____. - ANS-1
degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]
The temperature measuring device shall be calibrated _____, or whenever there is a question of
_____. - ANS-Annually, accuracy
The temperature of concrete may be measured in a wheelbarrow. True or False? - ANS-True
The temperature of concrete may be measured in a wall form. True of False - ANS-True
A composite sample of concrete is required even if the only purpose for obtaining the sample is
to determine temperature. True of False? - ANS-False
What must be done to the sample container prior to sampling the concrete? - ANS-Dampen
(with water)
What must be done to the concrete surrounding the temperature measuring device after the
device is submerged in the fresh concrete. - ANS-Gently press the concrete around the
temperature measuring device at the surface of the concrete
How long must the temperature measuring device remain in the freshly mixed concrete? -
ANS-At least 2 minutes but not more than 5 minutes
After the temperature of the concrete is read, what is required? - ANS-Reporting of temperature
The temperature of concrete is reported to the nearest _____ degrees F [_____ C] - ANS-1
degree F [0.5 C]
According to ASTM C1064, what is one reason to take the temperature of concrete? -
ANS-Verify conformance to a specified requirement for temperature of concrete
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True of False? -
ANS-False
The sample of concrete used for temperature determination must be rodded 25 times. True or
False? - ANS-False
, Sampling by this method is required when tests are to be made to determine _____ with
specification requirements. - ANS-Compliance
This method covers sampling from four types of mixtures which are _____, _____, _____, and
_____. - ANS-Stationary mixers, paving mixers, revolving drum mixers, and open top mixers
The maximum allowable time between obtaining the first and final portions of a composite
sample is _____ minutes. - ANS-15
Portions of a composite sample shall be thoroughly remixed bfore beginning tests on the
sample. True of False? - ANS-True
The maximum elapsed time allowed between obtaining the final portion of the composite
sample and beginning the tests for slump, temperature, and air content is _____ minutes. -
ANS-5
The molding of strength test specimens shall begin within _____ minutes after fabricating the
composite sample. - ANS-15
The concrete sample must be protected from contamination and _____. - ANS-Rapid
evaporation
The minimum size sample for making strength test specimens is _____. - ANS-28 L (1ft^3)
When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly
spaced intervals during discharge of the middle portion of the batch - ANS-2
The composite sample for a paving mixer must represent a minimum of _____ different portions
of the batch of concrete taken from the pile after discharge. - ANS-5
When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of
_____ regularly spaced intervals during discharge of the middle portion of this batch. - ANS-2
Concrete samples from a truck mixer must be obtained before any water or admixtures are
added to the mixer at the job site. True or False? - ANS-False
The composite samples from a truck mixer must be obtained from the _____ portion of the
batch. - ANS-Middle
When the concrete contains aggregate larger than that permitted for a particular test method,
the sample of concrete must be _____ _____ before making the test. - ANS-Wet sieved
The slump test is applicable to plastic concrete with a maximum size aggregate of _____. -
ANS-1.5 in. [37.5 mm]